Metrolinx considering alternate supplier amid court battle with Bombardier - Action News
Home WebMail Wednesday, November 20, 2024, 06:25 AM | Calgary | -10.3°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Toronto

Metrolinx considering alternate supplier amid court battle with Bombardier

Ontario transportation agency Metrolinx says it has been in discussions with an alternate light rail vehicle supplier as it continues a court battle with manufacturer Bombardier.

Talks with an unnamed company designed to ensure 'the urgent supply' of vehicles for the Eglinton Crosstown

Bombardier said in statement that it is able to deliver the vehicles on time by November 2018, well before the Eglinton Crosstown tracks are even built. (Metrolinx)

Ontario transportation agency Metrolinx says it hasbeen in discussions with an alternate light rail vehicle supplier asit continues a court battle with manufacturer Bombardier.

Metrolinx, which helps co-ordinate transportation in the greater Toronto and Hamilton area, said in an Ontario court filing Thursdaythat talks with an unnamed supplier are designed to ensure "theurgent supply" of vehicles for the Eglinton Crosstown line in Toronto.

It noted the number of potential suppliers is limited because it would have to comply with Canadian content requirements.

Metrolinx submitted the lengthy legal document, including affidavits, in response to an injunction filed last month by Bombardier that aims to prevent the provincial agency from terminating its $770-million contract for 182 vehicles.

It alleges that Bombardier (TSX:BBD.B) has repeatedly failed to deliver a prototype vehicle on time for the scheduled 2021 opening of the $5.3-billion line, citing deficiencies in Bombardier's operations in Mexico and Thunder Bay, Ont.

Metrolinx says Bombardier's injunction effort is a tactic to force it into months of litigation that would make it impossible for another supplier to provide the vehicles in time.

Bombardier responded by saying it rejects the allegations made by Metrolinx. The Montreal-based company says Metrolinx's reasons for wishing to end the contract have nothing to do with its ability to deliver.

Bombardier said in statement that it is able to deliver the vehicles on time by November 2018, well before the Eglinton Crosstown tracks are even built.

It says Metrolinx has refused to inspect the pilot vehicle since October and won't use a dispute resolution process included in the contract.