Iconic Toronto condo project placed into receivership due to $1.6B in unpaid debt - Action News
Home WebMail Monday, November 11, 2024, 05:22 AM | Calgary | -1.6°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Business

Iconic Toronto condo project placed into receivership due to $1.6B in unpaid debt

A high-profile Toronto condominium project that has been plagued with delays and setbacks for more than a decade has been placed into receivership by its biggest lender, refusing to foot the bill for $1.6 billion in unpaid debts until someone else is in charge.

Project has faced numerous delays and costs have ballooned to more than $2 billion

An under-construction condo tower.
The One, an 85-storey luxury condo under development at the corner of Yonge and Bloor, has been placed into receivership. The project was supposed to be finished already, but this is how it looked yesterday. (Cole Burston/CBC)

A high-profile Toronto condominium project that has been plagued with delays and setbacks for almost a decade has been placed into receivership by its biggest lender, refusing to foot the bill for $1.6 billion in unpaid debts until someone else is in charge.

The One, a proposed skyscraper at Yonge and Bloor, was taken over by a court-appointed receiver this week after the project's financiers defaulted on more than $1.2billion in loans on the project.

The land at the intersection of the two main thoroughfares in downtown Torontowas first purchased by developerSam Mizrahi for $300 million almost a decade ago, with plans to develop the site into a mixed-use retail, hotel and residential skyscraper with 85 storeys and 416 residential units a nod to the city's area code.

The project broke ground in 2017 with a planned completion date of 2018 for the retail portion on the lower floors, with the hotel and condos above ready by2022 at the latest.

Multiple delays

Since then, however, the project "has been plagued by delays and cost overruns," the lenders said in a filing. "Not to mention continual infighting between the principal investors in the project, both in and out of court."

That's a nod to a rift between Mizrahi and his partner on the project, investor Jenny Coco.

Mizrahi is a well-known developer in the city with multiple projects on the go, but Coco is perhaps best known for being the financier for Bridging Finance, an investment firm that was itself placed into receivership in 2021 by Ontario's securities regulator.

The main lenders for The Oneare a division of South Korean bankKEB Hana Bank, who have asked a court to assign someone to step in and take over the project to get it completed, or they won't extend their next payment on the project, for more than $315 million.

Earlier this month, the project's developersfailed to make paymentson more than $1.23 billion in loans, and hundreds of millions of dollars more are due soon, which prompted the legal action.

"To say that the project has been delayed and faced challenges would be an understatement," a court filing reads.

In addition to the more than $1.2 billion in loans already in default, another $130 million is owed to Canadian insurance company Aviva, filings show, whiletheChina-East Resources Import & Export Corporation a state-owned Chinese bank that was among the project's first lenders are owed $182 million.

WATCH | The proposed tower (from 9 years ago):

80-storey tower

9 years ago
Duration 3:35
A developer wants to build an 80-storey building at the former Stollerys site.

A dispute between the project's two backers, each of whom has a 50 per cent stake, is a major factor.

"Over the past several years, Coco's and Mizrahi's relationship has become increasingly acrimonious and dysfunctional," the lenders allegein court filings. "Their disagreements have impeded the ability of the borrower to complete the project."

"All of these problems are jeopardizing the Project, which is already delayed by at least two years beyond its original estimated completion date and still requires hundreds of millions of dollars of additional financing to complete," filings say.

Deal with Apple Store fell through

On the ground floor of the project, the original plan was to have the space be taken up by a massive 19,000-square-foot Apple Store, which would be the tech giant's flagship Canadian location.

But that agreement fell apart in 2021and "to date, the Borrower has not secured another tenant to lease the space that would have been occupied by Apple."

Partial view from high up of an unfinished luxury condo, with no exterior walls. It has been placed under receivership.
Three-hundred-and-forty-six residential suites have been sold so far at a collective price tag of$675 million. The other 70, all of which are for the 50th floor or above,have not. (Cole Burston/CBC)

The price tag for the project has ballooned from $1.4 billion to begin with to more than $2 billion today, with an opening planned for 2025 at the earliest.

Currently, construction has stalled at about 40 storeys, and while346 residential suites have been sold so far at a collective price tag of$675 million the other 70, all of which are for the 50th floor or above,have not. The remaining ones face tepid demand as the outlook for real estate in the city has significantly changed due to higher interest rates and a slowing economy.

At the request of the South Korean bank, restructuring firm Alvarez & Marsal has been appointedas the monitor for the proceedings. "The situation requires the assistance of an experienced court officer to bring stability to the project for the benefit of all stakeholders," a spokesperson for the bank said in an affidavit.

Mizrahi supports move

Mizrahi, for his part, supports the move.

"This is a welcome decision that will allow for the successful completion of The One under the continued leadership of Sam Mizrahi and Mizrahi Developments," his company, Mizrahi Developments.said inan emailed statement.

"At the request of the project's senior lender, the court has appointed a receiver to overcome an ongoing governance issue that has caused significant project delays.

The receiver has requested that Mizrahi and the company remain the developer and general contractor to oversee completion of the project, the statement said.Mizrahi maintains his equity position in the project, the company said.