Making highways resilient to extreme weather is the 'new normal,' B.C. transport minister says - Action News
Home WebMail Friday, November 22, 2024, 11:49 AM | Calgary | -10.8°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
British Columbia

Making highways resilient to extreme weather is the 'new normal,' B.C. transport minister says

British Columbia's transportation minister says 130 kilometres of highway that was severely damaged by flooding two years ago is now more resilient to extreme weather.

Repairs to Highways 1, 5 and 8 after destructive 2021 floods cost more than $1B

An aerial view of the Coquihalla Highway in B.C. shows the damage caused by flooding in 2021. The four-lane highway is cracked in half on a bridge over the river.
Damage caused by heavy rains and mudslides in November 2021 is pictured along the Coquihalla Highway near Hope, B.C. The province says repairs to the important trade route since then have made it more resilient to extreme weather. (Jonathan Hayward/The Canadian Press)

British Columbia's transportation minister says 130 kilometres of highway that was severely damaged by flooding two years ago is now more resilient to extreme weather.

Rob Fleming says the stretch of the Coquihalla Highway, or Highway 5, between Hope and Merritt, B.C., is an example of a "new normal"for how infrastructure needs to be built.

A series of atmospheric rivers in November 2021 triggered mudslides and washed out highways and bridges that blocked almost every route between B.C.'s Lower Mainland and the Interior.

Fleming says the cost to repair the damage caused to Highways 1, 5 and 8 is somewhere between $1 billion and $1.5 billion, but 70 to 90 per cent of that is expected to be covered by the federal government's disaster assistance program.

Jennifer Fraser, executive project director for the highway reinstatement program, says six bridges on the Coquihalla were replaced over 17 months.

She says some bridges have been made longer to allow more water to pass underneath, and crews strategically placed rocks and vegetation to help fight erosion.

Fraser says the bridges are also on stronger supports, with the longest pile being driven 65 metres into the ground.

Fleming says the highway, one of B.C.'s most important trade corridors, is now better able to resist future climate events.

"Our infrastructure has to be able to withstand extreme weather conditions. This is the new normal for the safety of our residents and the movement of goods throughout the province. This is an important infrastructure priority for British Columbia," Fleming said.