Staff with the VancouverBoard of Parks and Recreation are recommending theremoval ofthe 80-year-old pier at the city's Jericho Beach, citing climate change, upkeep expense and reconciliation goals as reasons.

Parks staff say climate change, upkeep expense, reconciliation are reasons to dismantle already-damaged pier

A man walks past a ruined pier on a beach.
The Jericho Beach Park pier in Vancouver pictured after it was damaged during a storm in January 2022. (Ben Nelms/CBC)

Staff with the VancouverBoard of Parks and Recreation are recommending theremoval ofthe 80-year-old pier at the city's Jericho Beach.

A reportmade public earlier this weeksays it would cost too much to repair or replace the pier, whichhas been closed since early 2022 due to significant storm damageand, the report adds,is at risk of more storm damage in future due to climate change.

"The pier is now at the end of its service life," reads the report.

The pierat Jericho Beach, on Vancouver's West Side, has in the past been a popular place to fish and take in views over the Burrard Inletand the downtown skyline, as well as a place for marine rescue vessels to dock.

But due to its extension from the shoreit has also been damaged by storms, most recently in November 2021 and January 2022.

A fence blocks off access to a damaged pier on a stormy day.
The pier was closed after strong winds and high tides in January 2022 caused significant damage. (Doug Kerr/CBC)

The report says these occurrences are expected to increase.

"Climate change is increasing the frequency of severe storm events, and sea level rise is expected to significantly impact this site," it said.

The plan in the report is for the pier to deconstructed but maintain its breakwater component so it would continue to shelter the nearby Jericho Sailing Centre.

In 2017, plans were floated to renew the pier, with a $16 million budget.With inflation and other costs, that plan could now cost as much as $25 million, the report says.

The park board said its budget has already been stretched with repairs to other infrastructure damaged in the 2021 and 2022 storms, such as the Stanley Park seawall and the Kitsilano Park waterfront walkway.

'Functional purpose'

For 30 years, theAdaptive Sailing Association of B.C. (ASABC) at Jericho Beach hasprovidedsailing opportunities for people with disabilities and used the pier as part of its programming, including mooring rescue boats.

"You could get out to people quicker," saidEric Molendyk, the ASABC program manager, on using the association's power boat to help people sailing if the wind died or there were other problems.

"It definitely served a functional purpose."

The association was part of a push to try to raise funds to renew and replace the pier, which would increase accessibility to the water and for activities such as those the association offers.

"Our hope as a program is that there is a functional rebuild, kind of a rebirth of the pier," said Molendyk. "Something new and better."

Reconciliation opportunity

If the plan is approved, the report says deconstruction could be an opportunity to meet reconciliation goals with local First Nations, as the location of the pier is on landsthat are "archaeologically, culturallyand ecologically significant"to theMusqueam, SquamishandTsleil-Waututhnations.

The removal of the pier could result in collaboration between the nations and the park board to restore naturalized areas where the pier is currently located.

The report also said the nearby Jericho Lands development, a housing developmentspearheaded by the three nations, requires a joint comprehensive planning study forJericho Beach Park.

"It will determine the best future plan for the park, including the site of the pier," said the report.

The cost to deconstruct the pier and maintain the breakwater is currently estimated at between $1.3 and $3.6 million.

The report says while simply repairing the pier is significantly less ($1.7 million), annual maintenance and repair costs are pegged at between $100,000 and $2.35 million.

"As a result, staff do not see this as a responsible financial decision due to the expected ongoing costs," reads the report, which will go before park board commissioners on Monday evening for a decision.