Aurora backs out, dealing another blow to B.C.'s LNG industry - Action News
Home WebMail Saturday, November 23, 2024, 12:14 AM | Calgary | -11.5°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
British Columbia

Aurora backs out, dealing another blow to B.C.'s LNG industry

Aurora LNG has backed out of a plan with Calgary-based Nexen to build a Liquefied Natural Gas plant in northwestern B.C., saying the current economy doesn't support its vision for a large operation on Digby Island.

'Strategic decision' ends vision of shipping 24 million tonnes of LNG to Asia every year

The Nova Scotia Utility and Review Board has approved a permit to build the Goldboro LNG plant in Guysborough County, clearing the way for Pieridae Energy to make a final investment decision on the proposed $5-billion project. (The Canadian Press)

Aurora LNG has backed out of a plan with Calgary-based Nexen to build a Liquefied Natural Gas plant in northwestern B.C., saying the current economy doesn't support its vision for a large operation on Digby Island.

It'sanother blow to the LNG industry that former premier Christy Clark promised would bring riches to B.C.during her provincial election campaign in 2013.

Of the 19 projects listed in April 2017 on thegovernment's LNG site, this project was one of only three which seemed to be moving forward.

Now there is onlythe Woodfibre LNG proposal near Squamish and the WesPac marine terminal on Tilbury Island in Delta.

In a news release today Aurora and its partners NexenEnergy and INPEXGas B.C. said they had made a "strategic decision" to end the feasibility study and cease all investigation activity immediately.

"The current macro-economic environment does not currently support the partners' vision of developing a large LNG business," said the release.

The $20-billion deal to buy the DigbyIsland site was aimed at eventually shipping 24 million tonnes of LNG product from B.C. to Asia every year.