Prince George city council approves $760,000 washroom - Action News
Home WebMail Thursday, November 14, 2024, 11:46 AM | Calgary | 6.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
British Columbia

Prince George city council approves $760,000 washroom

Split council voted 5-to-3 to increase the $500,000 budget by more than 50 per cent after project tender received just one bid from construction companies facing rising costs, labour shortages and supply chain issues.

Aging facilities in Carrie Jane Gray Park set to be replaced in time for 2022 B.C. Summer Games

Brown brick building with words
A motion to approvean increase of more than 50 per cent in the project's $500,000budget passed by a 5-to-3 vote at Prince George City Council Monday evening. (Andrew Kurjata/CBC)

Prince George city council has agreed to spend more than three-quarters of a million dollars to replace an aging public washroom in a park set to host the 2022 B.C. Summer Games.

A motion to approvean increase of more than 50 per cent in the project's $500,000budget passed by a 5-to-3 vote on Monday evening, and sparked council debate.

"When you put a price tag of $760,000, you kind of wonder whether it's gold plated or silver lined," said Prince George councillor Frank Everett.

The aging facilities in Carrie JaneGray Park were budgeted to be replaced in 2018, but were later added to the City Administration's 2022 Work Plan Priorities for the 2022 B.C. Summer Games.Hundreds of young athletes, familiesand spectators will crowd nearby baseball diamonds and playing fields in July.

"The current washroom facility is not useable, it's reached its end of life," Prince George Mayor LynHall told CBC News, noting the new 750-square-footbuilding will meet accessibility standards, and house equipment storage facilities for park staff.

Staff blame pandemic economics

A city staff report to council noted the project was tendered twice, but failed to attract competitive bids.

"Due to the turbulence in the construction market at that time it is plausible that construction companies were too busy to bid on the project. With labour and shipping concerns at that time, the bid may have been high. It was decided to re-tender the project at the beginning of 2022 just before construction season hoping to attract more competition and better pricing," the report stated.

Once again, only one bid was obtained, this time at twice the budgeted costs.

Hall notes municipalities are facing the same pandemic economic pressures asdevelopers andhomeownershoping to build.

"The supply chain, labour shortage, and increase costs of materials, we've not seen these increases ... in decades, if ever," Hall said.

"To the public, I understand that there's concerns about construction ... but that is what we're faced with. If you're going to construct any sized building you're going to face an increase in costs. And we do get to a point where we have to make a decision: are we going to move forward, or are we just going to let it go for two or three years and ultimately end up with more costs?"

Councillors Brian Skakun, Terri McConnachie, Kyle Sampson voted against the proposal.