CN trains rolling again after B.C. tracks repaired amid mounting backlogs

Amid growing backlogs, Canadian National Railway Co. trains are moving through southern British Columbia again after extensive flooding over the last three weeks.

Freight now flowing by rail in and out of the Port of Vancouver at critical time for grain export

A red and black CN train engine is seen on a railway, with an engineer standing on the train engine's platform.
A CN rail worker stands on a locomotive in Burnaby, B.C., on Nov. 27, 2020. Service between Vancouver and Kamloops was temporarily suspended after tracks were damaged by extreme weather in November 2021. (Darryl Dyck/The Canadian Press)

Amid growing backlogs, Canadian National Railway Co. says trains are moving again in southern British Columbia after the third atmospheric river in two weeks descended on the region.

CN says service resumed Sunday after crews worked around the clock on the Vancouver-Kamloops corridor, which was first cut by mudslides and washouts amid torrential rain in mid-November.

The country's largest railroad operator restored limited activity along the vital supply link late last month before opting to close the line again a week ago as more downpours triggered further flooding, landslides and debris.

"CN crews will continue to monitor both the rail infrastructure as well as the terrain over the coming days and weeks,'' CN spokesperson Jonathan Abecassis said in an email.

An aerial image of the Vancouver Port along Burrard Inlet.
An aerial view of the Port of Vancouver taken Nov. 21. Freight is now moving by rail again in and out of the city's port after service was suspended due to weather-related track damage last month. (Gian Paolo Mendoza/CBC)

The restored connection will allow freight to flow to and from the Port of Vancouver and begin to clear the massive backlogs of incoming shipping containers and outgoing grain.

The repaired lines will also allow Canadian Pacific Railway Ltd, which shares tracks with CN through part of the Fraser Valley, to boost its shipments.

End of year is a critical time for shipment of grain canola in particular with the bulk of Canadian grain transported via rail to B.C. ports.

Some can be diverted to Prince Rupert, B.C., the United States or Thunder Bay, Ont., but the window for the latter is nearly closed as winter ice looms, while rail cargo generally is hard to divert en masse.

"There are a few trains that are trickling through, but we don't have rail movements up to where we need them to be,"said Wade Sobkowich, executive director of the Western Grain Elevator Association.

"As far as a natural disaster goes, this is probably the most significant event to the rail lines in our collective memory."

Many farm deliveries to grain elevators have halted entirely as storage bins fill up and stakeholders await more detailed plans from the railways, Sobkowich said, adding he knows crews are working hard to ramp up traffic.

Grain strain

The backlog of Prairie grain may lose much of its value if trains can't ship it to port before spring, when prices typically drop amid heightened global supply, according to his association.

Contract extension penalties and demurrage fees issued by a shipping line when freight exceeds the time allotted at a terminal also present a threat for farmers and grain elevators trying to clear out brimming barns and silos.

"Regardless of when the traffic on the mainlines resume handling normal levels of traffic, the reverberations back through the grain supply chain in Western Canada (and all commodities) will be measured in months,"Steve Pratte, policy manager at the Canadian Canola Growers Association, said in an email.

The number of grain cars unloaded at West Coast ports dropped by 83 per cent year over year in the third week of November, according to the federal grain monitoring program's latest update.

As of Nov. 28, there were 24 grain vessels at berth or at anchor around the Port of Vancouver waiting for deliveries of up to 1.4 million tonnes of grain mainly wheat, canola and barley the update states.

Two CN trains are seen at a rail intersection in North Vancouver, B.C. (Jonathan Hayward/Canadian Press)

"These shipments are critical to ensure that Canadian farms get the cash flow required to cover the operating costs accumulated through the season, and it is a race against winter every year to try to get as much grain to port before winter conditions settle in,"Geoff Backman, markets manager at the Alberta Wheat and Barley Commission, said in a statement.

Many cargo ships also havebeenhampered from unloading their freight, and shipping containers are rushed back to Asia empty, says the Canadian Manufacturers and Exporters.

The number of empty cans through October was up 72 per cent from a year ago while exports were down 11 per cent, according to Vancouver-based GCT Global Container Terminals Inc.

No port, no profit

Other commodities are affected by the severe weather as well.

Teck Resources Ltd. said Monday that fourth-quarter coal sales could be as much as 24 per cent below expectations due to rail shipment disruptions in B.C.'s Lower Mainland.

The company will be able to recover much of the delayed sales in the first half of 2022, and Teck says ithas diverted shipments to the Port of Prince Rupert.

If wildfires, flooding and mudslides continue to increase amid the cascading effects of climate change, Canada's reputation as a reliable supplier could weaken, Sobkowich said.

"If you're a customer in the world and you need product for your mill or your processing facility, you need certainty of supply,"he said, notingthat strikes and rail blockades also factor in.

"If they've contracted to receive grain and they don't receive that grain, then it disrupts their ability to produce their products and it impacts their profitability. So they end up looking for sources elsewhere."

With files from Craig Wong