City officials said on Thursdaythat monitoring devices along the Bearspaw south feeder main have detected another new wire snap in the pipe since easing restrictions, which makes it three wires in totalthat have snapped.

'Not immediate cause for concern,' says city offical

construction workers stand around a large hole filled with muddy water as a large piece of construction equipment digs into the hole.
The Bearspaw south feeder main ruptured on June 5, and the catastrophic pipe failure left Calgary in a water-supply crisis. (Jeff McIntosh/The Canadian Press)

City officials said on Thursdaythat monitoring devices along the Bearspaw south feeder main have detected another new wire snap in the pipe since easing restrictions, which makes it three wires in totalthat have snapped.

However,Francois Bouchart, director of capital priorities and investment with the City of Calgary'sinfrastructure services department, says this doesn't mean the water main will have another catastrophic failure like it did over a month ago.

"Earlier this week, we detected two additional wire snaps within the pipe, and today we detected a third," said Bouchart.

"These snaps did not mean another break is imminent.The wire coils around each 16-foot (4.8-metre) segment of pipe approximately 350 times, and the snaps were spread across three locations along the feeder main."

Bouchart says that when crews discoveredfive "hot spots"along the feeder main,each section of pipe that was replaced had approximately 50 individual wire snaps per segment of pipe.

A massive water main pipe is shown, damaged and exposed.
The section of the Bearspaw south feeder main that ruptured is pictured here. The feeder main is a prestressed concrete cylinder pipe, a composite pipe material made primarily of concrete. (City of Calgary)

He says the city is aware it will need to create a longer-term plan for how to rehabilitate the sections of the pipe that are structurally weaker.

"The three additional snaps are not immediate cause for concern. However, they do show that the pipe is under some stress under the current flow conditions."

a blue background with a grey pipe. a diagram shows the parts of the pipe
A diagram shows the construction of the water feeder main. (City of Calgary)

The City of Calgary has been gradually lifting restrictions on water use,though officials continue tourgeresidents to ease back into their regular water-use habits as crewswork to fully stabilize the system.

Calgary remains underStage 3water restrictions as crews monitor how the city's watersystem will respond to the easing of water conservation measures.

On Wednesday, the city announced that all outdoor pools areexempt from the ongoingoutdoor water restrictions in order to help Calgarians seek some relief from the heat.

Bouchart said on Wednesday that Calgary's distribution system is able to meet water demand as long as Stage 3 outdoor water restrictions remain in place.

On Thursday, he saidthat in order to move to the next step of easing water restrictions, flow will need to be increased through the pipe, but crews are moving "very cautiously."

"We don't want to risk another significant break that could set back our progress," said Bouchart.

WATCH | City discusses pipe flow, pressure:

City provides update on water main break

1 month ago
Duration 24:05
City officials provide update on the major feeder main break affecting Calgary's water supply.

Water usage increasing during heat wave

Water use reached 555 million litres on Tuesday, up from the 540 million litres used Monday.

On Wednesday, that number climbed to 567 million litres.

City officials saythe Bearspawsouth feeder main which ruptured on June 5 isoperating at 55per cent capacity in terms of water flow. On Thursday afternoon, Bouchart said the pipe is experiencing roughly 80 per cent pressure.

Inorder to increase flow, crews need to be confident the pipe will be able to withstand the increased demand for water.