Alberta coal policy changes trigger joint lawsuit from coal companies - Action News
Home WebMail Wednesday, November 13, 2024, 03:37 AM | Calgary | -1.0°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Calgary

Alberta coal policy changes trigger joint lawsuit from coal companies

A trial date has been set for early 2025 to sort out whether Alberta is liable for billions in compensation due to policy changes forcoal development in the province.

4 separate statements of claim consolidated into single trial to start in early 2025

A hillside is shown with a number of trees along with a long gravel road.
A section of the eastern slopes southwest of Longview, Alta., on June 16, 2021. Several companies are seeking compensation after the province changed its laws regarding coal mining in the mountains. (Jeff McIntosh/The Canadian Press)

A trial date has been set for early 2025 to sort out whether Alberta is liable for billions in compensation due to policy changes forcoal development in the province.

In four separate statements of claim, coal companies allege that Alberta's decision in 2022 to change the rulesaround coal mining cost them financially and resulted in a "de facto expropriation" of their coal assets.

The companies involved in the action, which seeks a combined total in damages over $10 billion,are Cabin Ridge Holdings Ltd. and Cabin Ridge Project Ltd.; Atrum Coal Ltd., along with its subsidiary, Elan Coal Ltd.;Black Eagle Mining Corp.; and Montem Resources Ltd., which recently rebranded as Evolve Power Ltd.

In 2020, the Alberta governmentopened upmountains to more miningbut reversed course on that decision two years later.

Claims from the individual coal companies have been filed in the months subsequent to thepolicy change, but the consolidation of four separate actions was ordered in early November,as first reported by the Globe and Mail. The cases are scheduled to be tried either at the same time or one after the other, starting on or after March 31, 2025.

The companies' allegations have not been tested in court.

A man wearing a suit and tie stands in front of an Alberta flag.
A spokesperson for Brian Jean, Alberta's minister of energy and minerals, declined to comment on a lawsuit tied to the province's coal policy changes, citing the matter being before the courts. (Jason Franson/The Canadian Press)

Peter Doyle, president and CEO of Montem's Alberta operations, wrote in an email that his company was attracted to Alberta in 2016 to invest in the "valuable steelmaking coal resources" in the Crowsnest Pass, located in southwestern Alberta.

"We concentrated our investment on our assets where coal mining had occurred previously. We were confident we could responsibly restart and redevelop these old mines," Doyle said.

In its claim, Montemsaid the government's policy change and indefinite moratorium has resulted in the province acquiring "a benefit interest in or flowing from" the Montem properties.

"[It has] removed all reasonable uses of the Montem Properties by denying Montem the opportunity to continue the development of the Montem Projects and realize on those property rights," the claim reads.

Atrum Coal has said policy changescaused its share price to plummet. In its statement of claim, the company wrote that the Elan Project had an estimated 486 million tonnes of metallurgical coal and an approximate 34-year mine life, and developing Isolation South alone would see a valueexceeding$3.53 billion.

A spokesperson for Alberta Minister of Energy and Minerals Brian Jean said the province was "committed to protecting the areas Albertans cherish, while allowing responsible resource development where appropriate."

"We cannot comment on this, or any other matter, that is before the courts," James Snell wrote in response to a request for comment.

Claims face obstacles, says law professor

Nigel Bankes, an emeritus professor of law at the University of Calgary, specializes in natural resources and energy law.

He says claims ofde facto expropriation or "constructive taking"seek compensation on the claim the planned coal mines would havegone into production and produced profits over their lifespans.

But the law around such matters isn't that clear in Canada yet, he said.

A man wearing a hat looks at the camera with a backdrop of mountains pictured behind him.
Nigel Bankes, an emeritus professor of law at the University of Calgary who specializes in natural resources and energy law, said there is no constitutional protection of property rights in Canada. (Nigel Bankes)

"In Canada, it's clear that there is no constitutional protection of property rights. It's clear, therefore, that if the Government of Alberta wishes not to pay compensation, it can stipulate that by statutes," Bankes said.

"It can also say,'We will compensate on the basis of costs, rather than value.' So Iguess I'm saying it's certainly not a clear case."

Though the claims are seeking acombined total over $10 billion, they also suggest alternatives. For instance, in the case ofCabin Ridge Holdings Ltd. and Cabin Ridge Project Ltd., the claim suggests restitution in the amount of $56 million plus future and contingent remediation costs.

CBC News has reached out to representatives with Atrum, Black Eagle Mining Corp. and the Cabin Ridge project for comment.