Lake spill risk snarls Enbridge pipeline project after many delays - Action News
Home WebMail Monday, November 11, 2024, 12:51 PM | Calgary | 5.2°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Calgary

Lake spill risk snarls Enbridge pipeline project after many delays

Two state agencies have said they will hold up approval of the project's permits until problems with its environmental review are resolved.

Minnesota agencies hold back approval to resolve environmental review issues

FILE - This June 29, 2018 photo shows tanks at the Enbridge Energy terminal in Superior, Wis. Enbridge Energy's plan to replace its aging Line 3 crude oil pipeline across northern Minnesota has hit another obstacle. Earlier this month a court said the project's environmental impact statement failed to address the possibility of an oil spill into the Lake Superior watershed. Now the Minnesota Pollution Control Agency and Department of Natural Resources say they can't take final action on the project's permits until the Public Utilities Commission addresses the deficiencies. (AP Photo/Jim Mone, File)
Enbridge Energy's plan to replace its aging Line 3 crude oil pipeline across northern Minnesota has hit another obstacle. (Jim Mone/The Associated Press)

Enbridge Energy's plan to replace an aging crude oil pipeline that runs through northern Minnesota hit another obstacle this week when two state agencies said they would hold up approval of the project's permits until problems with its environmental review are resolved.

The Minnesota Pollution Control Agency and Department of Natural Resources said Tuesday that they can't take final action on the permits for the Line 3 project until the independent Public Utilities Commission (PUC) addresses the deficiencies cited in a state appeals court ruling this month, including that the project's environmental impact statement failed to address the possibility of a spill into the Lake Superior watershed.

That means the two state agencies won't release the draft permits as scheduled July 1, though they said they will continue reviewing the applications.

Calgary-based Enbridge said in a statement that the PUC will have to determine how to address the court's objections. The commission has not yet laid out a process or timetable for doing that.

Procedural delays and other court rulings have pushed back the project schedule several times.

"We believe the actions required to address the spill modelling in the Lake Superior watershed can be completed efficiently," the company said.

Winona LaDuke, executive director of the Indigenous environmental group Honor the Earth, which is an official party to the case, praised the pollution control agency and the natural resource department for making "a prudent decision to suspend their permitting process for a new pipeline that was never needed in the first place."

The $2.6-billion US replacement pipeline would carry Canadian crude from Alberta across northern Minnesota to Enbridge's terminal in Superior, Wis., which sits near the westernmost tip of Lake Superior.

Enbridge wants to replace the current Line 3, which was built in the 1960s, because it is increasingly subject to corrosion and cracking, and runs at only about half its original capacity for safety reasons.

Opponents warn of oil spill risks

Environmental and Indigenous groups fighting the project argue that it risks oil spills in pristine areas of the Mississippi River headwaters region where Native Americans gather wild rice, and that the Canadian oilsands oil that the line would carry accelerates climate change.

The Court of Appeals actually rejected most of the plaintiffs' objections to the environmental review, but they have until July 3 to seek further review from the Minnesota Supreme Court.

Other appeals are also pending, including one from the state Commerce Department, which has challenged the PUC's approval of the project, saying Enbridge didn't provide legally adequate demand forecasts to establish the need for the project. The PUC and Enbridge say the company did.

Jobs for Minnesotans, a coalition founded by business and labour groups, called on the PUC and other agencies "to work expeditiously through the final steps of the review process and move the Line 3 Replacement Project forward to construction."