Northern Gateway pipeline recommended for federal approval, with conditions - Action News
Home WebMail Tuesday, November 19, 2024, 02:22 PM | Calgary | -4.8°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Calgary

Northern Gateway pipeline recommended for federal approval, with conditions

A joint review panel has recommended the federal government approve Enbridge's controversial Northern Gateway pipeline project but only if it complies with 209 conditions.

Joint review panel says project in best interest of Canadians

Northern Gateway recommended for approval

11 years ago
Duration 2:38
A joint review panel is recommending the federal government approve construction of the proposed Northern Gateway pipeline, Briar Stewart reports

A jointreview panel has recommended the federal government approve Enbridge's NorthernGatewaypipeline project.

The approval hinges on 209 required conditions, including developing a marine mammal protection plan, researching heavy oil cleanup and conducting emergencyresponse exercises.

"After weighing the evidence, we concluded that Canada and Canadians would be better off with the EnbridgeNorthern Gateway project," said the panel in its roughly 500-page report.

The recommendationcomes after 180 daysof hearings in 21 communities in B.C. and Alberta.

The final decision, however, rests with the federal government, which has 180 days to decide. The government can approve or deny the application, but cannot change the conditions put forward by the panel. However, it can request the National Energy Board (NEB) to changethe conditions.

Enbridge president and CEO Al Monaco welcomed what he calleda tough review.

"Based on our preliminary look at the conditions of the recommendation, they're tough," he said. "But they should be, given everybody's goal to make sure we deliver a safe project and we protect the environment."

Enbridge said that if the project is approved that construction could start in 2014 and be completed by 2018.

'Science-based assessment,' says minister

The$7.9-billion pipeline would take bitumen from Alberta'soilsandsto the B.C. coast for tanker export to Asia. But the controversial proposal has pitted Calgary-basedEnbridgeagainst environmental groups and several First Nations.

The pipeline has also been a lightning rod in the debate over climate change and has raised concerns about the effects an oil spill would have on environmentally sensitive areas alongthe B.C.coast.

Natural Resources Minister Joe Oliver's office issued a statement after the approval, sayingthe project would not be approved by the government unless it is safe for Canadians and the environment.

The panels report represents a rigorous, open and comprehensive science-based assessment, reads the statement.

Now that we have received the report, we will thoroughly review it ...and then make our decision. We also encourage everyone with an interest to take the time and review the report.

The three-person panel was establishedin December 2009 by the NEBand the federal environment minister. Its task was to assess the environmental, social and economic effects from construction and operation of the pipeline.

In the past approval has come directly from the NEB, butcontroversial Bill C-38gave thatpower to cabinet.

B.C. sought5 conditions

TheB.C. government had told the panelit did not support the pipeline as proposed and it had five conditions that needed to be addressed.

B.C.'s 5 conditions

  • Environmental review needs to be passed.
  • World-leading marine oil spill prevention, response.
  • World-leading practices for land oil spill prevention, response.
  • First Nations opportunities, treaty rights respected.
  • Fair share of the fiscal and economic benefits for B.C.

George Hoberg, a University of British Columbia professor of forestry andethics, said the panel's decision is positive for the federal government, but it will be interesting to see where the B.C. government offers itssupport.

Whileinterprovincialpipelines are federal jurisdiction, Hoberg said, B.C. could launch a legal challenge.

He said the ConservativesneedB.C. seats to form a government after the 2015 election, so the question is whether there will be political war.

"It could go badly for [Prime Minister Stephen Harper] in the next federal election if they do," he said.

But there is still some support in the province as someBritish Columbia stakeholders celebrated the long-awaited announcement.

Aboriginal opposition still a factor

More than 130 aboriginal bands have signed a declaration against the project.

NDPLeader TomMulcairhas saidthevehement opposition from First Nations along the proposed route will eventually kill the project.

"This is not going to be allowed to go through without a peep,"Mulcairsaid Wednesday, faulting the Conservative government for ignoring the rights and concerns of aboriginal communities.

"You can no longer impose these things from the top down.This is another era. You need social adhesion, you need to work with people. You can't just bark at them and say, 'This is going through.'"

The opposition remains despite the fact thatEnbridgestarted consultations with First Nations in 2005, well before it filed anapplication for the pipelinein May 2010.

The federal government saysit willconsult with aboriginal groups now thatthe panel's report has beenissued.

Spill risk and wildlife impact

The report issued today saidthat although impacts of a large oil spill would be huge, the panel believes the conditions put on the project will help implement appropriate and effective spill prevention measures.

Enbridge has been directed to develop liability coverage of $950 million, but it would have to include many components such as having$100 million ready in cash to address the initial costs of a spill.

The panel's report also highlighted the risks posed to certain woodland caribou and grizzly bear populations.

Enbridge has put forth substantial mitigation plans, but the panel is not certain of the effectiveness of that mitigation.

One of the conditions for approval is a caribou habitat restoration plan.

The paneldid not address concerns about the Northern Pacific humpback whale because reports on the matter were not submitted as evidence during its proceedings.

Political reaction

Reaction to the decision has been mixed.

Alberta Premier Alison Redford had saidshe hopedthe panel would endorse the proposed pipeline as herprovince strives to diversify market access for theoilsands.

The panel also found that "opening Pacific basin markets is important to the Canadian economy and society."

Diana McQueen, Albertas energy minister, saidthe decision is an important step to reaching that goal and thatshe is confidentEnbridge can meet the needs of communities and First Nations in both provinces.

The Wildrose Party, Albertas official opposition, saidmeeting all of the 209 conditions in the report will ensure the provinces resources can be developed safely and protect the environment in B.C. and Alberta.

But the Pembina Institute is calling today's decision disappointing.In a release, the organization saidthe panel's report is out of step with Canadians' concerns about the oilsands and pipeline development.

It says the review panel excluded the environment impacts of further oilsands development and that the greenhouse gas emissions resulting from filling the pipeline will be the same as adding three million cars a year to Canadianroads.

Both thefederalNDPand Liberals have voiced opposition to the project.

Chat replay:

With files from The Canadian Press