Wildfire hands Suncor a $735-million loss, cuts Q2 oilsands production in half

Fierce wildfires that swept through northern Alberta's oilsands region in May have delivered a $735-million net loss for Suncor Energy.

Company spent $50 million related to evacuation and restart activities

Suncor President and CEO Steve Williams speaks to the media after meeting with Alberta Premier Rachel Notley at the Alberta Legislature in Edmonton on May 10. (Amber Bracken/The Canadian Press)

Fierce wildfires that swept through northern Alberta's oilsands region in May have delivered a $735-million net loss for Suncor Energy.

The Calgary-based company said late Wednesday the fire that raged through the region meant it failed to produce about 20 million barrels of upgraded and raw bitumen from its oilsands projects. It said it spent $50 million related to evacuation and restart activities, offset by $180 million in cost savings while operations were suspended.

President and CEO Steve Williams said in a news release the company focused on evacuating employees and their families during the fire. After personnel were allowed to return to the projects, the focus turned to restarting operations and completing a maintenance turnaround at one of its base mine upgraders, with all operations back to pre-fire productivity by mid-July.

Suncor's net loss for the three months ended June 30 equated to 46 cents per share. A year earlier, it reported second-quarter net earnings of $729 million or 50 cents per share.

The company recorded a second-quarter 2016 operating loss of $565 million, compared with operating earnings of $906 million in the same period last year.

Total second-quarter production was 330,700 barrels of oil equivalent per day, compared with 560,000 boe/d a year earlier. Total oilsands output was 177,500 barrels per day, less than half of 423,800 bpd in the second quarter of 2015.