$34B Trans Mountain expansion pipeline begins filling with oil with first shipments before Canada Day - Action News
Home WebMail Sunday, November 10, 2024, 11:08 PM | Calgary | 0.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Calgary

$34B Trans Mountain expansion pipeline begins filling with oil with first shipments before Canada Day

The odyssey of developing and building the Trans Mountain expansion project in Western Canada is finally nearing the finish line as sections of the pipeline begin filling with oil.

After 12 years and $34 billion, the Trans Mountain expansion project is nearing the finish line

Workers lay pipe during construction of the Trans Mountain pipeline expansion on farmland, in Abbotsford, B.C., on Wednesday, May 3, 2023.
Workers lay pipe during construction of the Trans Mountain pipeline expansion on farmland, in Abbotsford, B.C., on Wednesday, May 3, 2023. Its first export shipment will happen before Canada Day, although Alberta's premier expects it could become operational as soon as May. (Darryl Dyck/The Canadian Press)

The odyssey of developing andbuilding the Trans Mountain expansion project in Western Canada is finally nearing the finishing line as sections of the pipeline begin filling with oil.

The first export shipment will happen before Canada Day, the federal Crown corporation said, although Alberta's premier expects it could become operational as soon as May.

The Trans Mountain is Canada's only oil pipeline to the West Coast.The project will transport oil from Alberta to the West Coast and triple the amount of crude that is shipped on an existing pipeline, from 300,000 barrels per day to 890,000 bpd.

Canadian oil prices are expected to increase once the new project is completed. Court challenges, regulatory hurdles, multiple protestsand constant delays are all part of the history of the project, which began more than a decade ago.

Then there's the cost.

When the federal government stepped in to purchase the project six years ago and rescue it fromlife support, the estimated price tag was $7.4 billion. Today, expenses are $34 billion.

'What a long, strange trip it's been'

On stage Wednesday at the CERAWeek energy conference in Houston, Trans Mountain chief financial officer Mark Maki used a bit of humour when describing the project's past, knowing full well how eye-popping the cost escalation and multiple setbacks have been for Canadian taxpayers and the industry alike.

"I reflect on some lyrics from a Grateful Dead song:'What a long, strange trip it's been.' Twelve years from beginning to in-service. That's too long," he said, drawing laughter from the crowd, beforehe proceeded to list the many challenges such as the regulatory process, the pandemic, floodsand wildfires.

WATCH|The climbing costs of the TMX pipeline:

A post-construction review of costs should be done on TMX

2 months ago
Duration 3:28
Lessons could be learned on how the Trans Mountain expansion pipeline was developed and built, says company CFO Mark Maki.

Currently, less than 25 per cent of the pipeline is filled with oil, said Maki, in sections ofwhere construction took placeseveral years ago.

He suggests there should be a post-construction cost review to see whatlessons can be learned about developing large-scale projects in Canada.

"It is expensive to do the project right. That's what it costs to build infrastructure," he said, in an interview with CBC News in Houston.

Pipelines cross long distances, and can impact several Indigenous communities and develop previously untouched land.

"For all those reasons, we have to understand better, whoever you are, what it really is going to cost to build infrastructure."

The final price tag, he said, could still changeas remaining work is completed. The company has said it will need approximately three months following the completion of construction before it can provide a definitive cost estimate.

On Wednesday, Bloomberg reported a Chinesestate-owned company, Sinochem Group, hadpurchased one of the first crude cargoes to move through the new pipeline.

A woman sits in a chair at a hotel conference room.
The Trans Mountain expansion is expected to increase the value of Canadian oil, which should increase the amount of royalties collected by the Alberta government, says Premier Danielle Smith, in an interview with CBC News in Houston at CERAWeek by S&P Global. (Kyle Bakx/CBC)

Construction crews have focused recently on overcoming difficulties drilling through rock in B.C.'s Fraser Valley between Hope and Chilliwack and pulling the pipe into the hole.

The final piece of pipe is expected to be installed in the next few weeks, said Maki. Next steps include work on some above ground facilities, the testing and inspection process, and satisfying some regulatory requirements.

Despite all the issues over the years, Maki is adamant the project will have a positive impact on the oilpatch, the economy, Indigenous communities and government coffers.

"We're happy. We're getting to the end and that's a reason to be proud and we're doing something that I think is good for the country," he said.

Opposition to the project

Some environmental critics have argued the project will impact waterways and marine animals, while promoting expansion of the oil industry. The national regulator has previously said theproject would cause "significant adverse environmental effects" on the southern resident killer whale population,while also highlighting the potential of a pipeline leak or tanker spill.

Theexpansion is expected to result in a seven-fold increase in the number of oil tankers traveling through the waters around Vancouver and Victoria.

People protest outside, holding signs opposing a pipeline expansion. One protester holds an inflatable of a black and white orca whale.
A man holds an inflatable of an orca whale above the crowd as protesters opposed to the Trans Mountain pipeline expansion listen during a rally ahead of a decision by Liberal cabinet on the project, in Vancouver, on Sunday June 9, 2019. (Darryl Dyck/The Canadian Press)

Trans Mountain has support from dozens of Indigenous communities along the pipeline route, but others have been strongly opposed, even launching years-long court challenges.At one point, the project was halted because of a lack of consideration of Indigenousconcerns.

Expanding domestic oil production

This year, Canada is expected to lead the world in oil production growth.

"It's going to make a big difference to our producers. It's going to make a big difference to us as a government since we charge our royalties based on [oil prices]," said Alberta Premier Danielle Smith,in an interview in Houston.

Prime Minister Justin Trudeau made the right decision to purchase the project six years ago, she said.

"I'm pleased that they stepped in to de-risk and finish the project," said Smith, adding how Ottawa ideally would have supported other pipelines to ensure they, too, were built, such as Energy East and Northern Gateway.

A complete Trans Mountain expansion will increase the amount of pipeline export capacity, although industry leaders say any spare space will be filled.

"Some were wondering, 'When TMX is done, will Enbridge not have as much supply going through its pipes?' We're hitting records. I expect that you'll see all of our assets continue to be used," said Enbridge's CEO Greg Ebel.

Some analysts have said the country's export pipelines could be full again in a few years, continuing the growing oil production in Western Canada.

A man sits in front of a large poster showing natural gas pipes, solar panels and wind turbines.
Canadian oil export pipelines will remain full as oil production climbs, says Greg Ebel, Enbridge's chief executive. (Kyle Bakx/CBC)