Home | WebMail | Register or Login

      Calgary | Regions | Local Traffic Report | Advertise on Action News | Contact

Sign Up

Sign Up

Please fill this form to create an account.

Already have an account? Login here.

EdmontonVideo

Metro LRT Line will finally open Sept. 6

City transportation manager Dorian Wandzura announced the trains will operate at lower speeds. The trip from NAIT to Churchill Station will take 14 minutes.

The $700-million line to NAIT is now more than 15 months behind schedule

Metro Line LRT to start running Sept. 6

9 years ago
Duration 5:43
City transportation manager Dorian Wandzura announces the trains will run at reduced speeds

The Metro LRT line to NAIT will finally open for service on Sept. 6.

Citytransportation manager DorianWandzura announced the trains will operate at 25 km/hr to allow operators to use a "line of sight" style of operation

Wandzura said lower speeds will allow LRT operators to stop the train"in half of their field of distance."

The tripfrom NAIT to Churchill Station will take 14minutes, instead of seven.Wandzura said the trip willbe two minutes faster than the existing express bus. Trains will run at 50 km/hr once the system is fully operational.

Wandzura said guard rails will go down at crossings.

"The line is safe," he said. Operators will start their training on Monday.

Wandzura wasn't able to say when the system would be at full capacity. The city will have to add an extra train to the line which will increase costs. Every third train coming from Century Park station will be diverted to NAIT. This will mean a 17 per cent loss of capacity from Churchill station north to Clareview station.

Mayor Don Ivesonhas long expressedfrustration over the ongoing delays. Hereacted somewhat tepidly to Friday's announcement.

"No cause for celebration yet," he said on Twitter. "Only when it's fully operational and yegcc's[Edmonton city council has] gotto the bottom of why it was delayed."

Coun. Ben Henderson said council wanted the line open for the start of the school year at NAIT and MacEwan University so he was pleased a solution was found.

Justin Nand, president of NAIT's student association, is pleased to hear the Metro Line will be open for the start of classes. (CBC)
"It's not ideal," he said. "It's not exactly what we want but it was getting very frustrating knowing the rest of the line was ready to go and we were just waiting for the signalling system."

Justin Nand, president of the student association at NAIT, didn't expect the line to open this fall.

"I was a little surprised but very happy and very enthusiastic to have LRT running to some capacity now in September for the students to use," he said.

Nandisn't concerned about the slower trains.He said taking just one train to school is better than having to transfer to a buseven if it makes the trip a little longer.

Owners of businesses around Kingsway Mall are also relieved. Construction on the line has caused trafficcongestion andparking problems.

"Parking hasbeen an issue for some of our businesses with students from NAIT and maybe people using the hospital andother facilities," said EllieSasseville, executive director of the Kingsway District Association.

"So obviouslythe access will hopefully eliminate some of that issue for many of the businesses in the area.So we're looking forward to that."

The Metro Line was supposed to open in the spring of 2014.Problems with integrating the new andoldsignallingsystemsdelayed the opening of the $700-million line.

Thaleshad the contract to design and build the line. The company gave the city a safety certificate in March. However, after performing a review, the city held back on putting the line in service.