Official hired to protect city's interests in Winnipeg police HQ project got $105K 'kickback': lawsuit - Action News
Home WebMail Wednesday, November 13, 2024, 04:36 AM | Calgary | -1.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Manitoba

Official hired to protect city's interests in Winnipeg police HQ project got $105K 'kickback': lawsuit

The City of Winnipeg alleges in a recent court filing the director of its downtown police headquarters project an official hired to look after the city's interests received a $105,000 "kickback" from the main contractor on the job.

In another new allegation, city also claims subcontractor received $1M in 'project profits'

Ossama AbouZeid, seen here in a 2011 file photo, was the project director for the Winnipeg police headquarters project. The City of Winnipeg alleges in a May court filing that he received a $105,000 'kickback' from a company controlled by police HQ contractor Armik Babakhanians. Both are defendants in a city lawsuit. (The Canadian Press)

The City of Winnipeg alleges the director of its downtown police headquarters project an official hired to look after the city's interests received a $105,000 "kickback" from the main contractor on the job, according to a recent court filing.

That allegation is part ofa notice of motion filed May 4 as part of the city's ongoing lawsuit against contractor Armik Babakhanians, his company Caspianand dozens of other defendants.

The city claims police headquarters project director Ossama AbouZeid and his company Dunmore received $105,000 from Mountain Construction, a Babakhanians-controlled company.

In a civil judgment, Manitoba Court of Queen's Bench has already ruledthat former Winnipeg chief administrative officer Phil Sheegl received a bribe when he accepted a $327,200 payment from Mountain Construction.

Sheegl, who was ordered to pay the city $1.1 million in damages, plans to appeal that decision, his lawyer Robert Tapper has said.

The city launched its lawsuit in January 2020, alleging more thantwodozen defendants were involved in a"scheme" offraud, embezzlement and kickbacks related to the construction project.

The latest court filing seeks to amend the city's claimby adding more allegations, people and companies to the lawsuit, which contends the defendants conspired to inflate and overcharge for work on the $214-millionproject.

In the new filing, the city claims Mountain transferred the funds to AbouZeid and Dunmore in April 2011.

That was one month before Dunmore's contract with the city started, and several months before Caspian was awarded a $137-million contract to renovate aformer Canada Post warehouse building into the new Winnipeg Police Service headquarters.

A large blue rectangular building.
The City of Winnipeg has sued dozens of people and companies involved in the construction of its police headquarters for what it describes in court documents as a 'scheme' to defraud taxpayers. (Tyson Koschik/CBC)

The city claims in the filing the money was transferred "with the knowledge that Dunmore and/or AbouZeid were agents of the city"in a business relationship with other defendants"at the time the kickbacks were issued, in order to influence them to procure one or more of the defendants other unfair procurement advantages."

In earlier court filings, the city called AbouZeid and Dunmore "co-conspirators" with Sheegl and Babakhanians. Those documents allege Sheegl helped ensure a Winnipeg Police Service employee was removed as a project manager on the police HQ project and AbouZeid was hired as project director.

The city's court filings include excerpts from email exchanges between Babakhanians and Peter Chang, an official who worked for the structural engineering firm Adjeleian Allen Rubeli.

Chang is also being sued by the city.

Chang wrote to Babakhanians to vent his frustrations with the project in 2012, according to the court filings.

Babakhanians wrote back to Chang, saying"I have Ossama there because he brings no other value than agreeing to anything also he is on that board of some city related issues,"according to the court filing.

"Unfortunately he became a toy in the hand of cops," he wrote. "So guys I have many projects lined up just do me proud let's get this crap out of way."

Email correspondence between Armik Babakhanians and Peter Chang in 2012, included in court documents, discusses the role of Ossama AbouZeid on the police HQ project. (Manitoba Court of Queen's Bench filing)

AbouZeid's legal counseldeclined to address the kickback allegations.

"We have no comment regarding the proposed pleading amendments. We will respond in court," Jamie Kagan said in a statement.

"Our client denies any and all wrongdoing and quite frankly is not the focus of the litigation."

Subcontractor got$1M in 'project profits': city

In another new allegation in the May court filing, current Winnipeg chief administrative officer Michael Jack claimsPeter Giannuzzi, Jr. a police HQ subcontractor already named in the city's lawsuit received two $500,000payments from Mountain Construction, the Babakhanians-controlled company.

Jack says in the filing that the city obtained an email exchange between Giannuzzi Jr. and Armik Babakhanians' son Shaun Babakhanians,whom the city is also suing. A spreadsheet was attached to that correspondence.

Peter Giannuzzi refers to 'project profits' in a note to Shaun Babakhanians of Caspian, the police headquarters contractor, according to court documents. (Manitoba Court of Queen's Bench filing)

In that spreadsheet, Giannuzzi referred to, among other things, "minor home improvements [being] written off on projects" and "project profits" of approximately $12.5 million related to the police headquarters project, Jack says in the filing.

The spreadsheet calculates Gianuzzi's"total anticipated compensation"at just over $1.6million, the filing says.

The city also has a copy of a January 2014 invoice submitted by a Giannuzzi Jr. company6820540 Manitoba Ltd. to Caspian for "Consulting & Quantity Services, Multiple Projects,"Jack says in the court document.

The filing also seeksto add Giannuzzi's father, Peter (Pietro) Giannuzzi, Sr., of the firm G&G Interiors Ltd., to the list of defendants.

Court documents include this invoice from a Giannuzzi-controlled company to Caspian Projects. (Manitoba Court of Queen's Bench filing)

Forensic accountant's audit

The city hired forensic accountant Victor Neufeld to do an audit of police HQ records.

Neufeld said he found Caspian claimed nearly $8 million for G&G invoices related todrywall work on the police HQ, according to a May 4 affidavit.

However, Caspian payments to G&G totalled less than $6 million, Neufeld's affidavit says.

"[Caspian] apparently claimed more than $2 million above its total identified payments to G&G in respect of its drywall work," Neufeld wrote.

The city's previous court filings say Peter Giannuzzi Jr. and hisnumbered company wereshareholders in yet another company named in the lawsuit, Fabca-PMG Projects Ltd.

It was incorporated in July 2013, during the construction of the police HQ.

That was months after Caspian had already submitted the last known Fabcainvoice to the city,according to a January 2020 Neufeld affidavit.

Giannuzzi Jr. was also a Caspian employee and on-site project manager, according to a Caspian organization chart included in the court documents.

Neufeld's 2020 affidavit alleged that Caspian billed the city for $20.7 million worth of work it said Fabcacompanies conducted on the police HQ.

"It is unclear how Fabca could perform, without assistance from or involvement of other parties, the volume of Fabca-invoiced work given that Fabca had only 4 persons security-cleared to do project work," the court document stated.

TheGiannuzzisandBabakhaniansdid not comment to CBC News.

The city's lawsuitremains before the Court of Queen's Bench.

Prior to thecivil lawsuit, the police headquarters project was the subject of two external audits and an RCMP fraud and forgery investigation.

That investigation, which spanned five years, ended in 2019 with no charges laid.

Official hired to protect city's interests in Winnipeg police HQ project got $105K 'kickback': lawsuit

2 years ago
Duration 1:25
The City of Winnipeg says in court documents that an official hired to look after the city's interests during the construction of the Winnipeg police headquarters, received a kickback from the contractor.