Winnipeg's southwest rapid transit corridor expansion cost drops $120M
The projected cost of extending Winnipeg'ssouthwest rapid transit corridor has shrunk by $120 million.
The savings were realized through some changes to the final design and a competitive bidding process, city officials said, addingthe project was also advertised during "very favourable market conditions" that included lower interest rates and a lowervolume of work in the national marketplace.
Construction of the extension will begin this summer, with Plenary Roads Winnipeg heading up the $467.3-million project.
Building a rapid transit system in #Winnipeg is building our city for the future: https://t.co/myZEg4VkfE pic.twitter.com/L1WXDmjUjY
—@Mayor_Bowman
The existing southwest rapid transitcorridorruns from downtown to Jubilee Avenue and Pembina Highway.The extension will add7.6 kilometres, from Jubilee to the University of Manitoba.
The project is expected to be completed in late 2019 and will then go through a period of testing as well as training of drivers.
Transit operations on the new corridorare expected to begin in April 2020.
Very encouraged to see $120 million in savings identified for second phase of bus rapid transit: https://t.co/71r8JQvxNM
—@Mayor_Bowman