Red River College shelves plans for $95M innovation centre

Red River College has put the brakes on a $95.4-million expansion project at its campus in Winnipeg's Exchange District.

College says deadline imposed by federal government is impossible because of work needed on heritage building

An artist's rendering shows the inside of the proposed innovation centre. (Number 10 and Diamond Schmitt)

Red River College has put the brakes on a $95.4-million expansion project at its campus in Winnipeg'sExchange District.

"RRC's decision to halt construction of the four-storey, 100,000-square-foot Innovation Centre is the result of a disagreement with the federal government over what constitutes a reasonable timeline for completion of the major infrastructure project involving a heritage building in downtown Winnipeg," said college spokesman Conor Lloyd.

An artist's rendering shows a design for the proposed Red River College Innovation Centre. (Number 10 and Diamond Schmitt)
Red River College has already torn down the former Metro Motors garage, where it intended to build the four-storey innovation centre. The three-storey warehouse next to it is the heritage building the school intended to renovate. (Google Street View)

To keep the federal contribution of$40.6 million, the project slated to be built on Elgin Avenue would have to be completed by Nov. 30. The funding agreement wassigned and finalized at the end of June 2017, he said.

We still very much want to proceed, but we need to iron out this deadline disagreement with the feds first before we can carry on with construction, and we are very hopeful that we will find a solution- ConorLloyd

Meeting that deadline is impossible because the project involves the renovation of a heritage building, which requires complex and time-consuming work, Lloyd said, adding thatRRChas been working to get a deadlineextension but the government has been unwilling to grant it.

As a result, the companies working on six tenders for the project have been told to discontinue, at least for the time being.

"We still very much want to proceed, but we need to iron out this deadline disagreement with the feds first before we can carry on with construction, and we are very hopeful that we will find a solution," said Lloyd.

Work already completed includes demolition of 325 Elgin (the former Metro Motors garage) andremediation of the site, consultations with more than 100 user groups, refining of the centre's design, site surveysand traffic flow studies.

"The Innovation Centre would allow Manitoba to keep pace with other provinces that are investing in similar centres and moving away from old-style classrooms and learning," Lloyd said.

This illustration shows another interior view of the innovation centre. (Number 10 and Diamond Schmitt)

"The centre's focus is on innovation, entrepreneurship and collision space creative interactions between students, faculty, business, applied research and the community."

The centre would bring more than1,200 additional students, staff and faculty to the college. It also would be a significant expansion of RRC's Exchange District campus, which has included the restoration of several heritage sites and helped revitalizethe neighbourhood, Lloyd said.

A spokesperson with federalInnovation Minister Navdeep Bains's office saidthe original pledge was part of the federal Post-Secondary Institutions Strategic Investment Fund, first launched in 2016.

The program was meant to stimulate short-term economic activity and support long-term innovation and environmental projects.

Red River submitted an application for funds for the Innovation Centre prior to April 30, 2018, the federal spokesperson said.

"Recently, the program initiated a process whereby projects can apply for an extension toNov. 30, 2018, in response to unforeseen delays in the construction process," a statement from Bains reads.

"This extension remains consistent with the original objectives of the program."