No completion date in the pipe for $795M North End sewage-plant upgrades - Action News
Home WebMail Saturday, November 23, 2024, 12:44 AM | Calgary | -11.5°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Manitoba

No completion date in the pipe for $795M North End sewage-plant upgrades

A massive sewage-treatment project ordered up by the province in 2003 won't be finished by the City of Winnipeg until the 2020s.

Construction schedule under review for most expensive capital project in Winnipeg's history

Winnipeg no longer knows when it will finish $795 million worth of upgrades to the North End Water Pollution Control Centre. (CBC)

A massive sewage-treatment project ordered up by the province in 2003 won't be finished by the City of Winnipeg until the 2020s.

Upgrades to the North End Water Pollution Control Centre, the largest of Winnipeg's three sewage-treatment plants, won't begin in earnest until after 2019, water and waste officials concede in a report published on Monday.

The $795-million project the most expensivecapital-construction jobin the city's history involves building two new facilities at the North End sewage treatment plant.

One facility willremovephosphorus and nitrogenfrom the effluent produced by the North End sewage-treatment plant. Right now, these nutrientswindup in the Red River and are carried northto Lake Winnipeg, where they promote the growth of algae that alters the ecology of the lake.

The other facility will dispose of biosolidspartly treated solid waste produced by all three of the city's sewage plants.

The provincialClean Environment Commission ordered Winnipeg to build both facilities in 2003 after it conducted hearings into a 2002 mechanical failureat the North End plantthat resulted in 427million cubic metres of untreated, unfiltered sewage spilling into the Red River.

That order also called for upgrades at the West End and South End sewage plants. The former have been completed and the latter are in the works.

But in a report headed to city council's finance committee on Friday, Winnipeg's water and waste department says it doesn't even know when construction will begin on the North End Water Pollution Control Centre upgrades.

"The project schedule for the NEWPCCupgrade is under review. The project completion date of December 2019 is not achievable," writes Geoff Patton, engineering manager for Winnipeg's water and waste department.

The report states the city plans to issue a request for proposals to consulting firms interested indesigning and building the project in 2018 and intends to award thecontract in 2019.

The report doesnot indicatewhen the project will be completed. Requests for interviews with water and waste officials were denied on Monday.

St. Vital Coun. Brian Mayes, who chairs council's water and waste committee, said he intends to ask this precise question of city officials when his own committee meets on Tuesday morning.

"This is now expected to be the biggest project in the city's history and they're telling me they don't know the answer," Mayes said on Monday.

In the past, the province has chided the city for the slow pace of conducting sewage-treatment upgrades. The city was warned to get going on the South End upgrades as recently as November.

The city, meanwhile, has complained intermittently thatBroadway and Ottawa have not contributed their fair share of the funds needed to complete the upgrades. To date, they've been financed primarily by increases to the city's water-and-sewer bills.