Going over instead of under helped Winnipeg keep rapid-transit costs down - Action News
Home WebMail Monday, November 11, 2024, 05:55 AM | Calgary | -1.6°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Manitoba

Going over instead of under helped Winnipeg keep rapid-transit costs down

Replacing tunnels with overpasses helped shave $120 million from the cost of completing the Southwest Transitway, project managers say.

Winnipeg Transit divulges more details on tweaks to the design of the Southwest Transitway's second phase

An artist's conception showing part of the second phase of the Southwest Transitway, showing the new crossing at Jubilee Avenue and a widened Pembina Highway. (City of Winnipeg and Plenary Roads Winnipeg)

Replacing tunnels with overpasses helped shave $120 million from the cost of completing the Southwest Transitway,project managers say.

On Monday, Winnipeg Transit unveiled the latest design for a five-year project that involves extending the city's first transit corridor to the University of Manitoba and widening the Pembina Highway underpass at Jubilee Avenue to six lanes.

Last month, the city disclosed the project cost is now pegged at $467 million instead of $587 million. Winnipeg Transit project managers Scott Payne and Jesse Crowder say construction consortium Plenary Roads Winnipeg was able to remove $120 million from the tab by making several changes to the design.

The biggest design change involves scrapping plans to build a bustunnel below a pair of rail lines between ChevrierBoulevard and Plaza Drive. Anoverpass will cover the rail lines instead.

A second tweak getsrid of a bike-and-pedestrian tunnel initially planned for a ramp atJubilee Avenue underpass.The active-transportation corridor will be re-routedalongside theramp instead.

The third change involves keeping a Bishop GrandinBoulevardrail bridgethat was initially slated for demolition to make room for both a bus and bike-and-pedestriancrossing. The new design wouldsee a separate bike-and-pedestrian path rise to the west of the rail bridge, as long as CN Rail and Manitoba Hydro agree.

Winnipeg Transit hopes to begin construction on the Southwest Transitway this summer. (Jamie Clemis/CBC)
Winnipeg Transit asset managerScott Payne, the outgoing project manager responsible for the SouthwestTransitway, said these changes emerged as a result of a competitive city search for a private partner capable of designing, building, financing and maintaining the 7.6-kilometre second phase of the bus corridor.

"It brought in companies from right across Canada and even theUnited States to bid on this project," Payne said of the search.

"So we hadinterest from allacross North America in terms of their horsepower to design, to build,to construct. So we sawa lot of innovative ideas in part of ourproposals for all three of our bidders and those innovations amountedto a significant saving."

Details of the design changes will be presented to the public on Tuesday at an open house slated for 4 to 7 p.m. atCanad Inns Fort Garry, 1824 Pembina Hwy.

The design now calls for a total of seven overpasses or bridges but no tunnels whatsoever. It also calls for a relocated Brenda LeipsicDog Park featuring proper draining, walking paths and a paved parking lot, Crowder and Payne said.

IGF Station to open next spring

It still calls for nine new rapid-transit stations, including a bus-corridor stop at Investors Group Field. Winnipeg Transit hopes that stop along with a section of transitway that runs through the former Southwood Golf Course landwill be ready in time for the 2017 Canadian Football League season, which begins in June,and the Canada Summer Games later that summer.

Work on the Southwood section will begin in August. Winnipeg Transit saysPlenary Roadswill start widening Pembina Highway to six lanes later this year.

"We had a lot of incentives in the contract to minimize those lane disruptions [and] lane closures and we're going to have to see [that] the contractor keepsa minimum amount of lanes open," said Crowder, the incoming Southwest Transitway project manager.

The project is expected to be substantially complete in October 2019 and be open in 2020.Mobile users: View the document
(PDF KB)
(Text KB)
CBC is not responsible for 3rd party content