No way out: Recent gas leak highlights Cte Saint-Luc's need for Cavendish Extension - Action News
Home WebMail Thursday, November 14, 2024, 11:44 AM | Calgary | 6.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Montreal

No way out: Recent gas leak highlights Cte Saint-Luc's need for Cavendish Extension

With money set aside and a willingness at all levels of government to bring the Cavendish Extension to life, realization of the project has been firmly anchored in the negotiation phase for decades and those negotiations have been extended yet again.

'We definitely need another route out,' says Mayor Mitchell Brownstein as negotiations continue

The Sept. 6 gas leak in Cte Saint-Luc caused major gridlock throughout Montreal's west end, making it a struggle to get in and out for motorists and emergency crews alike. (Navneet Pall/CBC)

Cte Saint-Luc resident MichaelLitvackwokeon Sept. 6 to discover his bedside clock had stopped working at around 8:15 a.m.

It quickly became apparent he was among the more than 10,000 Hydro-Qubec customers in Montreal's west end withoutpower after authorities shut it off due to a gas leak near the intersection of Kildare Road and Cavendish Boulevard.

As a crew repaired the broken gas pipe and nearby residences were evacuated, the Cavendish Boulevard underpass one of just two ways out of Cte Saint-Luc was only accessible by side streets.

The main part ofCte Saint-Luc is surrounded by train tracks and a rail yard, making the underpasses on Cavendish and Westminster Avenuethe only two routes out of a suburban municipality of more than 30,000 people.

CteSaint-Luc's roads are generally quietbut, with one underpass partially blocked, the gas leak ignited a traffic nightmare. Gridlock around both underpasses lasted for several hoursdespite the Montreal fire department's request that motorists avoid the area.

"People in my part of Cte Saint-Luc were stuck," said Litvack, who struggled to get a blood test that day. "Businesses had to close. Schools had to close. Doctors appointments had to be rescheduled."

Cte Saint-Luc's Cavendish Boulevard underpass is regularly busy with motorists, trucks, buses and pedestrians as it is one of the only ways out of the city. (Isaac Olson/CBC)

It served as a stark reminder of how Cte Saint-Luc's design leaves it vulnerable, he said.

The municipality has seen big changes in the last decade as new homes and residential buildings are added every year. Several large-scale, multi-storey apartment complexes are currently under construction and there is talk of more on the way.

"It's going to get worse," Litvak said. "As the cars increase and the people increase, the problems will increase."

The Westminster Avenue underpass is one of Cte Saint-Luc's two access points. (Isaac Olson/CBC)

There are four emergency gatesthat allow vehicles to drive over train tracks, but opening them requires coordination with the train companies.

The best solution, most say, would be a third exit to the north, heading to Montreal's Saint-Laurent borough and the Town of Mount Royal, but the so-called Cavendish Extension has been firmly anchored in the discussion phase for some five decades those discussions were delayed two more years earlier this week.

Mayor says Cavendish Extension is in the works

After the gas leak, Mayor MitchellBrownsteinhas been reminding residentsthat he is workinghard on bringing the Cavendish Extension to life.

"We definitely need another route out," he told CBCNews.

It is nolonger a question of if,it is a question of when, said Brownstein,noting he'smade it atop priority since assuming office in 2016.

The project has been in Montreal's capital work budget since 2015 with a completion date originally set for 2020. Currently, Montreal has $13 million earmarked for the cause and money is set aside at the provincial level as well.

While Canadian Pacific (CP)is asking for a costly tunnel under the entire rail yard, Brownstein said he, along with the other levels of government, is pushing for two underpasses under the two separate tracks just north of Cavendish Boulevard.

Rather than being an alternate to the nearby Decarie Expressway, it would be a quieter, ground-level roadway that, fitting with the neighbourhood's character, connects CteSaint-Luc to Mount Royal's Royalmount Avenue and St-Laurent's section of Cavendish Boulevard.

The indirect routewould follow a to-be-built, fenced-in road through the rail yardand a small portion of private land owned by the property developer, Olymbec.

The properties owned by Olymbec are in the starred area. (Google Maps)

Montreal reserved that undeveloped land for expropriation and, on Thursday, the agglomeration council extended the reserve foranother two years,to buy time for Montreal to continue its negotiations with CP.

The future of the Cavendish Extension hinges on those negotiations negotiations that have been ongoing for a number of years.

"We just need to keep pushing to get the proper road built that isn'ta highway, but allows us a way out of our city," said Brownstein.The renewed two-year extension on the reserved land, he added, means "everybody is on a timeline."

A stretch of Cavendish Boulevard in Cte Saint-Luc was closed due to a Sept. 6 gas leak that created a traffic jam so bad that Montreal's fire department struggled to access the site. (Navneet Pall/CBC)

However, Montreal also extended negotiations by another two years Tuesday and MNA David Birnbaum described thatdecision as "disappointing" becauseit green lights further delays.

"We have always said and continue to say, we will be absolutely and fundamentally involved in the development of the Cavendish Extension," he said, describing it asnot only important for the safety of residents, but also for the economy.

He said he's called meetings between all the players involved to accelerate the process and the province has been offering support.

"We're all ready to be a major part of this project and it's time for it to move forward."

For that to happen, he concluded, Montreal needs to complete negotiations with CP.

When contactedfor more information about the negotiations anddelays, CP spokesperson Jeremy Berry said CP continues to work closely with local officials on this matter.

To help push the project forward, CteSaint-Luc Coun. David Tordjman is encouraging residents to raise their own voices to the cause as, he said,the gas leak brought safety to the forefront of the discussion.

With Quebec's general electionheating up and Canada's election just around the corner, he said,"We need more firm action from all levels of government."