Feds reveal new Champlain Bridge name the Samuel De Champlain Bridge

The bridge, which will link Montreal to the South Shore, will now carry the full name of the explorer it's already named after.

Span linking city to the South Shore only slated to open by June

The new Champlain Bridge will open by June 30, 2019, according to the federal government. (Ainslie MacLellan/CBC)

The federal government has confirmed that when it opens, the new Champlain Bridge will have a new, if familiar,name.

The bridge, linking Montreal to the South Shore, will be known as the Samuel De Champlain Bridge the full name of the Frenchexplorer the old bridge is named after.

"The new name follows the example of other bridges in Montreal, which include the full names of the historic figures they honour,"Franois-PhilippeChampagne, the federal Infrastructure Minister, said in a news release.

It was originally supposed to open to traffic Dec. 1, but that date was pushed back to Dec. 21, then pushed back again to June 30, 2019, at the latest.

During a progress update in October, the consortium building the bridge said the main structure would be done by the due date, but the waterproofing and paving work could only be doneafter the winter.

"We're just adjusting the last 60 cm to have the bridge fully joined, so we're on schedule," Champagne said.

"This is one of the biggest construction sites in North America. Under extreme weather conditions, we've been able to deliver."

As part of the contract signed between the government and the consortium, Ottawa could fine Signature on the Saint Lawrence (SSL), the consortium buildingthe bridge, $100,000 for every day the bridge is late for the first week, and $400,000 daily after that, up to a maximum of $150 million.

Champagnesaid the government is in discussions with the consortium to determine when the penalties will kick in.

"We will be enforcing the terms and conditions of the contract," Champagne said."When there are delays, there are consequences."

In October, there was a 37-metre gap in the bridge that still had to be closed. This is what's left of that gap. (Ainslie MacLellan/CBC)

The new bridge will cost upwards of $4 billion.

The existing Champlain Bridge opened in 1962 andwill eventuallybe demolished.About $50 million was spent on maintaining the old bridge in 2018, and another $10 million of work will be done to ensure its safety until thenew bridge opens.

Matt Jeneroux, the federal Conservative Party'sinfrastructure critic, criticized Champagne and the Liberal government for their lack of transparency in committee discussions about the Champlain project.

"Wasting money on today's non-announcement and continuing to excuse these delays demonstrates just how out of touch this government is," Jeneroux said in a statement.