Lakeshore General Hospital opens interim ER to maintain services during construction - Action News
Home WebMail Sunday, November 10, 2024, 07:50 PM | Calgary | 0.9°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Montreal

Lakeshore General Hospital opens interim ER to maintain services during construction

For the next 24 hours, staff at Montreals Lakeshore General Hospital are going to be busy as the emergency room and all of its patients are moved to a new, temporary facility.

Modular emergency room was built in 7 months to provide space for patients during hospital renovations

man preparing gurney
Staff at Lakeshore General Hospital in Montreal are getting the new modular emergency room ready for patients, which are expected to arrive Wednesday. (Davide Gentile/Radio-Canada)

For the next 24hours, staff at Montreal's Lakeshore General Hospital are going to be busy as the emergency room and all of its patients are moved to a new, temporary facility.

"Some of the equipment is still arriving," said Dan Gabay, president and CEO of the West Island health agency, the CIUSSS de l'Ouest-de-l'le-de-Montral.

"We're hoping to have a full start on Wednesday, and do some fine tuning in the week after."

The modular emergency room, built in seven months, provides a lot of sunlight, and the open space is designed so nurses can easily see their patients, he said. The structure was installed in the hospital'sparking lot.

The old ERwas built in the 1980s, and not only are there air exchange issues, it was built in a way that doesn't allow nurses a proper line of sight on patients, said Gabay.

The revamped ER is slated for opening in 2028, with major renovationsbeginning next year.

During construction, a temporary space was needed, he said, noting it will have the same amount of stretchers, but a new workflow.

building
The modular ER was built in seven months as the hospital readies for a 10-year renovation project which will continue even after it reopens to patients in 2028. (Davide Gentile/Radio-Canada)

The more spacious, modularERhas allowed for some services to be reconfigured for the better, said Gabay.

Quebec Health Minister Christian Dub was on site Monday, touring the temporaryER. He said it is an important day for the West Island.

"I think we have been able to prove in the last year that we could find a more efficient way to renovate our infrastructure," he said.

"This new emergency was put in place in seven months, and I think this is quite an accomplishment for the team."

two people work on hospital equipment
Crews have been testing the new equipment to ensure it is ready for the patients set to arrive on Wednesday. (Davide Gentile/Radio-Canada)

In an effort to improve efficiency, there will be a family clinic attached to the ER. The University-affiliated Family Medicine Groupisa project in collaboration with McGill University. Itwill allow triage to redirect patientswho don't need ER services, the health minister said.

"I think that's quite the change to make sure we put the patient at the right place with the right professional," said Dub.

In recent years, some Lakeshore employees have spoken out about alarming situations, such as not having enough staff for the number of patients in the ER.

Last year, Dub commissioned an independent report on the hospital's ER, which recommended urgent renovations to protect patient safety. It's not uncommon for the ER to exceed 200 per cent capacity.

On its busiest days, the ER is so stretched for space that patients on gurneys line not just every hallway, but even the narrow passageway in front of the nursing station.

More recently, the family of an 86-year-old woman who was found dead on the ER's floorin 2021 is suing the CIUSSS de l'Ouest-de-l'le-de-Montral for $1 million. The lawsuit also names an ER doctor and a nurse.

The CIUSSS says on its website that thenew permanentERwill be a three-storey building that includes38 stretchers in cubicles, a 12-bed, short-term hospitalization unit for physical health and a six-bed, short-term mental health unit.

"Once completed, the new emergency department will be a modern, functionaland integrated space that maximizes the care and services provided and supports patients' recovery," the website says.

with files from Mlissa Franois