Home | WebMail | Register or Login

      Calgary | Regions | Local Traffic Report | Advertise on Action News | Contact

Montreal

More workers hired to ensure new Champlain Bridge will be completed on time

The consortium in charge of building the new Champlain bridge says the span will be finished on time.

An extra 200 workers were hired this summer to meet December 2018 deadline

There are 850 people working around the clock to finish construction of the new Champlain Bridge by December 2018. (Radio-Canada)

The consortium in charge of building the new Champlain bridge says the span will be completedon time despite being six to nine months behind schedule.

Signature sur le Saint-Laurent says it's pickingup the pace with more workers on the site working around the clock so that the new bridge will be completed by the end of next year.

The new Champlain Bridge will have two lanes for vehicles and one lane reserved for public transit. (Radio-Canada)
"We went from 650 workers to almost 850 workers over the last three months. So now we can increase the number of shifts on the site," said Daniel Genest, head of the consortium Signature sur le Saint-Laurent.

The $4-billion project is behind schedule due in part to the public engineers'strike last spring, which lasted several weeks.

Also, a sudden change in provincial standards, which prevented transport trucks carrying heavy loads from taking the old Champlain Bridge, further delayed the work.

The consortiumis suing the federal government for nearly $124 million, alleging it wasn't forewarned that the existing bridge couldn't bear the weight required to transport important pieces to the worksite.

The new span will have 600 steel beams and more than 9,600 concrete slabs. (Radio-Canada)
If the new bridge is not completed on time, the bridge corporation says it would cost up to $250 million to keep the old span safe enough to use after that point.
Once the new ChamplainBridge is delivered,demolition of the old one is expected to begin in 2019 and take about four years to complete.
The Champlain Bridge is the busiest span in Canada. The new one will cost $4.23 billion. (Radio-Canada)

The new bridge's expected lifespanis 125 years.