TransCanada work on St. Lawrence port suspended by Quebec court order

Four environmental groups have won a temporary injunction to stop exploratory work by TransCanada to develop an oil port in Cacouna, near Rivire-du-Loup, on the St. Lawrence River.

Environmental groups say project threatens beluga whales near Cacouna, Que.

Barges have already arrived in Cacouna, Que., to start the exploratory work, but a court injunction prevents TransCanada from proceeding until Oct. 15. (Radio-Canada)

Four environmental groups have won a temporary injunction to stop exploratory work by TransCanada to developa port inCacouna, near Rivire-du-Loup,on the Saint Lawrence River.

The groups argued theTransCanadapipeline project threatens a nursing ground for beluga whales.

"The judge agreed with us, and I think that is a clear testament to the fact that the Quebec government needs to go back and do its homework;needs to seriously consider the science that's widely available on this endangered species," saidPatrick Nadeau, spokesmanfor the Canadian Parks and Wilderness Society, one of the groups that sought the injunction.

Work had startednearCacounaearlier this month, but lawyers representing the David Suzuki Foundation, Nature Quebec, the Canadian Parks and Wilderness Society and the Quebec Centre for Environmental Lawfiled an injunction to stop the drilling.

The company wants to builda petroleum port atCacounaandis in the process ofchecking soil composition to see where to place a terminalthatwould take in crude being transported via thepipeline to refineriesin Eastern Canada.

On Tuesday, a Quebec Superior Court judge suspended the certificate of approval issued by the province and ordered all work to stop immediately.

The judge found that Quebec's environment minister, David Heurtel,made an error in granting the permit, saying he did not have enough information to do so.

"That's essentially what the judge decided today:that the minister issued a permit but didn't have the proper information to do so," Nadeau said.

A spokesperson for the environment minister saidHeurtel won't comment because the matter is before the courts.

Delay to reduce risk

The court ordered the Alberta-based company to ceasework untilOct. 15. The environmental groups had requested that date becausethe belugas are considered to be most at risk during that period.

Nadeau said the groups will continue their fight to halt the project permanently.

TheTransCanadaEnergy East pipeline project includes converting an existing natural gas pipeline to an oil transportation pipeline.

This project is controversial and Quebec's environmental assessment boardis still reviewing it.

Barges have already arrived inCacounawith crews ready to study the seabed for the port project.