Cosmetic job for Moncton's subway overpass to cost $573,000 - Action News
Home WebMail Thursday, November 14, 2024, 10:38 PM | Calgary | -3.6°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
New Brunswick

Cosmetic job for Moncton's subway overpass to cost $573,000

A Moncton landmark and hazard for tall vehicles will get a $573,000 facelift this summer.

Council approves cosmetic upgrades for Main Street structure ahead of events centre opening

A rendering of how Moncton's subway overpass could look after cosmetic upgrades that will cost $573,000. The work will include adding LED lights, signs, a fresh coat of paint, new sidewalks and railings. (City of Moncton)

Monctonwill spend more than $573,000 forestheticupgrades at the subway overpass, adding new lighting, brick sidewalks and fresh paint.

Citycouncillorsunanimously voted at a special meeting Thursday afternoon to award the contract worth $573,183, including tax, to Modern Construction Ltd. for work on the structure owned by CN where its railwaycrosses above Main Street.

The contract includes sidewalk improvements, paint, LED lighting, electrical, signs, planting trees and shrubs and new metal railings.

The spending won't address vehicles crashing into the low overpass.

The structure has a clearance of 11 feet, or about 3.3 metres, and tractor-trailers and recreational vehicles occasionally get jammed while trying to drive along Main Street.

The subway overpass has a clearance of only 3.3 metres and has caught a few trucks and recreational vehicles over the years.

AlcideRichard,Moncton's director of design and construction, said staff are looking at ways to reduce the risk of large vehicle-drivers getting stuck.

"It's not an easy one. We've looked at laser beams and lights," Richard said, adding staff hope to return to council with ideas by this fall.

"I find it hard to spend this much money and we don't have a concept to stop the damage being done,"Coun. Bryan Butler said.

Richard said once the visual upgrades are done, the city will likely be required to cover maintenance costs while CN will remain responsible for the structure itself.

That worriesCoun. ShawnCrossman, who voted in favour of the work.

"That's an icon inMoncton,"Crossmansaid. "There's nothing wrong with investing, but it's an asset that's owned by CN."

Crossmanasked staff if CN will cover any of the cosmetic upgrade costs.

"That's dialogue we're having with them at this moment," said Marc Landry, the city manager.

Among the different looks tried on by the subway was the pink look, created in the 1970s. (Vintage Moncton)

The city hopes the work will be completed before the downtown events centre opens in September.

"A safe and highly visible pedestrian corridor is required to create linkages to private and public parking areas in the downtown area," says a staff report to council.

The spending on the subway was not part of the $113-million cost of the 8,800-seat arena and outdoor plaza.

Mayor Dawn Arnold described the appearance of the pedestrian portion of the subway as "Third World" in a May interview.

The staffreport says the overpass installed in 1915 is considered structurally sound, though freezing and thawing have caused concrete to chip and fall away.CN has paid to make repairs to the structure.

In the1970s, the subway was painted pink with murals painted on panels underneath the structure.