More than 4 years behind schedule, $58.9M stretch of Team Gushue Highway set to open

Phase 2 will link Kenmount Road to Topsail Road.

Kenmount-Topsail connection expected to open in late November, with Phase 3 still in the planning stages

A road with a single yellow line in the middle. Rock walls rise on either side.
Phase 2 of the Team Gushue Highway is set to open soon, with Phase 3 from Old Brookfield Road to Goulds Bypass Road still to come. (Ted Blades/CBC)

In the coming weeks, Phase 2 of the Team Gushue Highway will be complete, linking Kenmount Road to Topsail Road.

The entireproject announced in 2006 after Brad Gushue of St. John's and his curling rink won an Olympic gold medal in Turin, Italy was initially projected to be completed by 2014. Now, Phase 2 is expected to be opened by the second half of November with Phase 3 still in the planning stages, according to Transportation Minister Steve Crocker.

"It's a substantial construction project. You'll see by the numerous overhead structures, and when you look at building overpasses ... it takes, in most cases, twoto threeyears to complete these major concrete structures," Crocker told CBCNews.

The cost of the highway from the Outer Ring RoadtoKenmountRoad was$11.6 million, split evenly betweenthe provincial and federal governments at 50 per cent each.

The cost of the highway fromKenmountto Topsail Road is$58.9 million, withthe federal government contributing $22.5 million and the provincial government coveringthe rest.

The Department of Transportation pegs the total cost of the constructionof the Team Gushue Highwayfrom the Outer Ring Road to Topsail Road at$70.5 million.

Displacing traffic

There's still a lot of finishing work to be completed before an exact opening date can be provided, said Crocker, but the section of highway is very close to being completed.

St. John's Coun. Jamie Korab and provincial Transportation Minister Steve Crocker take a tour of Phase 2 of the Team Gushue Highway. (Ted Blades/CBC)

"You can probably get fromKenmountRoad toTopsail Road in two to three minutes doing to the speed limit," said St. John's Coun. Jamie Korab, a member of the highway's gold-medal-winningnamesake.

"It is going to take cars off Columbus Drive, it's going to take cars off Kenmount Road, it really will move cars. And, I believe the figure I heard before there could be somewhere between 20,000 and 22,000 cars drive this daily."

The Brier

The Brier will get its own piece of real estate on the Team GushueHighway, lending its name to a new avenue that will be an offshoot of the bypass.

The Gushuerink won thethe annual Canadian men's curling championship in St. John's in 2017, and although Korabwasn't a part of that squad, he says it's a fitting name to be part of the cross-city highway projecthonouring Gushue and his squads.

With files from On the Go