$1.3M in daily interest: Why further Muskrat Falls delays matter - Action News
Home WebMail Friday, November 22, 2024, 03:01 PM | Calgary | -10.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
NL

$1.3M in daily interest: Why further Muskrat Falls delays matter

Every day the completion date for the Muskrat Falls project is delayed costs N.L. Hydro and the provincial government $1.3 million in interest and other financing charges.

New schedule sets overall completion date for Muskrat Falls at end of March

Top down view of a hydro dam in Labrador on a nice sunny day.
In another setback, the completion date for the Muskrat Falls project has been delayed until late March, and every day the project is delayed, hundreds of thousands in interest and financing costs are added to the price tag. (Nalcor Energy)

Lingering uncertainty continues over when the troubled Muskrat Falls project will be finished, but one thing is certain: every day the project is delayed, the costs continue to go up.

Newfoundland and Labrador Hydro has confirmed that thebill for interest and other financing charges on the billions it has borrowed to construct the generating station and transmission lines is $1 million per day.

In addition, the provincial Department of Finance has revealed that it is being hit with $300,000 in daily interest charges for the money taxpayers have poured into the project.

It's sobering news for a project that is already more than $6 billionover budget, years behind schedule, and has forced the federal government to offer up billions in support to prevent electricity rates from doubling when the project is finally commissioned.

The issue of financing charges is significant because the overall completion date has once again suffered a setback.

N.L. Hydro confirmed in October that the Nov. 26 finish date is not achievable, largely because GE Grid Solutions is struggling to perfectthe software used to operate the 1,100-kilometre high-voltage direct-current transmission line from Labrador to Newfoundland's Avalon Peninsula, known as the Labrador-Island Link.

A steel electrical tower in the middle of a snowy field on a clear day.
These steel towers support the 1,100-kilometre Labrador-Island Link transmission line from Muskrat Falls to Soldiers Pond on Newfoundland's Avalon Peninsula. The company contracted to develop a specialized software to operate the link, GE Grid Solutions, is struggling to fulfil its contract. (Terry Roberts/CBC)

In an update to the province's utility regulator last week, N.L. Hydroset a new completion target of late March, which could add125 days to the schedule if the project is not commissioned until March 31.

N.L. Hydro officials continue to assess the financial impact of the Labrador-Island Link delays, say a spokesperson.

N.L. Hydro president and CEO Jennifer Williams has acknowledged delays will likely drive up the final forecast cost of the project, currently pegged at $13.1 billion, but said last month, "I don't expect it to be material."

In a followup statement, Hydro officials said all costsanticipated to be paid to GE, and the cost of maintaining a "skeleton project team" into 2022,"are contained in the current estimate."

There's also a contingency allowance. "Any potential increase in the total project cost estimate would result if there are costs that fall outside of that contingency, primarily the interest payments referenced," said the statement.

The extra financing costs "will be recoveredover the life of the asset through electricity rates," the Hydro official wrote.

Muskrat Falls is a Nalcor-led hydro generation and transmission project sanctioned in 2012 at a cost of $7.4 billion, featuring an 824-megawatt generating station on the Lower Churchill River, and the Labrador-Island Link.

In addition, Emerahas constructed the Maritime Link between Newfoundland and Nova Scotia, with a capacity of 500 megawatts and a 35-year guarantee of 20 per cent of the energy from Muskrat Falls.

But the Muskrat Falls project hasbeen plagued by delays and controversy, and was the subject of a commission of inquiry that labelled it a misguided project.

In June, the provincial government announced that Nalcor was being swallowed up by N.L. Hydro, with a new, leaner executive team announced last week.

As a public project, the provincial government has committed to funding any cost overruns, and so far has invested $4.4 billion, with $3.5billion of that borrowed, according to the Finance Department.

In addition, Nalcor has financed the project through $7.9 billion in borrowing that's been guaranteed by the federal government.

Meanwhile, Hydro's update to the PUB last week exposed a growing level of frustration with GE.

With the Nov. 26 completion date no longer achievable, GE set a new date of Dec. 31 for commissioning of the control and protection software. But Hydro expressed a lack of confidence in that schedule, writing that it considers GE's schedule to be optimistic "based on their performance to date," and that March is a more reasonable timeframe.

Read more from CBC Newfoundland and Labrador