Home | WebMail | Register or Login

      Calgary | Regions | Local Traffic Report | Advertise on Action News | Contact

NL

Plunge in oil price, demand pushes Nalcor to $137M loss after 2nd quarter

Despite a $37 million second-quarter profit, Nalcor is still trying to recover from a $171-million loss in the first quarter.

2nd quarter profit of $37M not enough to make up $171M loss in 1st quarter

Nalcor CEO Stan Marshall says power from Muskrat Falls could start flowing within the next month. (Terry Roberts/CBC)

A steep drop in oil production and demand under the COVID-19 pandemic is still impacting Nalcor Energy's bottom line, as the provincial energy corporation Thursday announced a $137-million loss after its second quarter.

It's a much different situationfrom the same time frame in2019, when the corporation recorded a profit of $119 million.

Despite a $37-million profit in the second quarter of 2020, the company is still dealing with a first-quarter loss of$171 million.

With Thursday's release of the second-quarter financial results, NalcorCEO Stan Marshall said completion of the troubled hydroelectric megaproject isin sight, and could, within a month, begin producing power, which will then be sold to lower costs for electricity users in Newfoundland and Labrador.

Butgetting power to Newfoundland willtakea bit longer.

A problem with the transmission software the Labrador-Island Link is still being ironed out.

Marshall saidGeneral Electric the company working on the software is still working out the kinks, but added he feels better about the projectthan he has ina long time.

"They worked throughout the COVIDperiod, which is very positive. Obviously they've had some productivity lost because of COVID,but we're now past a critical phase," said Marshall.

"We've tested all aspects of the software in the factory acceptance tests. We've identified certain bugs which they're still working on, but we've got a version now that allows us to load. We have loaded. We have tested. We began testing."

Work was suspended at Muskrat Falls and the Soldiers Pond transmission centre in March due to the pandemic, but resumed in June. As a result of the interruption, project completion has been delayed by four months.

But there could be a further delay of two to six months,,depending on the level of productivity and the number of workers allowed on site as a result of COVID-19 guidelines this fall, Marshall added.

Marshall said another version of the software is due this fall, but the final version isn't due until next spring.

Testing of the Labrador-Island Link software will continue over the next few months, with power intermittently coming to the island, he said.

Marshall saidit's difficult to estimate how much power will actually flow in that time, but it could be a lot.

Top down view of a hydro dam in Labrador on a nice sunny day.
Nalcor Energy is reporting a loss of $137 million in the second quarter of 2020. (Nalcor Energy)

"It'll start within the next month, and before the thing is finally commissioned there should be a substantial amount of power delivered," he said.

"The revenue from that, the proceeds from that, will help mitigate rates."

Commissioning work and an inspection is underwayatUnit 1, said Marshall, and the second unit is expected to be online before the end of 2020.

A loss

Marshall said he will give an update at the end of September on the full effect of the COVID-19 pandemic on the cost and the schedule of the project.

To date, the project has cost $11.5 billion.

In March, Husky Energy announced the suspension of construction on the West White Rose Project due to COVID-19. Marshall saidengineering, preservation and maintenance, and some procurement activities have continued while the project is under review.

"As of the suspension date, the project was approximately 58 per cent complete," he said. "Production remains steady at White Rose, as well as at the Hebron and Hibernia fields, and all facilities are operating with enhanced screening provisions and physical distancing measures for site workers."

Marshall said he met withandbriefed Premier Andrew Fureylast week onwhere the Muskrat Falls project stands.

Read more from CBC Newfoundland and Labrador

Corrections

  • A previous version of this story stated Nalcor had a second straight quarter with a loss of more than $100 million. The story has been changed to reflect a $37-million profit in the second quarter, balanced against its first-quarter loss.
    Aug 21, 2020 7:10 AM NT