Construction of new arena in Yukon village delayed until 2021 - Action News
Home WebMail Friday, November 22, 2024, 09:50 PM | Calgary | -11.3°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
North

Construction of new arena in Yukon village delayed until 2021

The Government of Yukon said it has issued a notice of default on the performance bond against the contractor Scott Design Build in a news release Tuesday. It's now looking for a solution to get work started again on the Carmacks arena as soon as possible.

Contractor hasnt restarted work this spring following a planned winter shutdown

A view of a large arena under construction.
A photo of the Carmacks arena in November 2019. Awarded in 2018, the plans for the new, year-round facility include a full indoor arena, community spaces and a link to the existing recreation centre. (Government of Yukon)

The new arena planned for Carmacks, Yukon, will likely be delayed until 2021.

Originally slated to open in August 2020, construction on the arena has not restarted this spring following a planned winter shutdown.

The territorial governmentissued a notice of default on the performance bond against the contractor Scott Design Build and is now looking for a solution to get work started again as soon as possible,according to a governmentnews release Tuesday.

Awarded in 2018, the plans for the new, year-round facility include a full indoor arena, community spaces and a link to the existing recreation centre. The building is designed to meet or exceed energy efficiency standards in a northern climate.

The $16.55 million project is a joint venture between the Government of Canada and the Government of Yukon, with the federal government contributing $10.5 million and the territorial government contributing $6.05 million

So far, $8 million has been spent on the project. A Government of Yukon official said in an email that it's still too early to say how much the delay will cost the project.

Any work done in order to complete the project will need to comply with COVID-19 measures, including having workers self-isolate for 14 days if they arrive from out of territory.

The government said a local contractor is monitoring the site.

Subcontractors or suppliers who haven't been paid should contact the Procurement Support Centre to file a claim.