Inuvik to Tuktoyaktuk highway construction to resume in January - Action News
Home WebMail Monday, November 11, 2024, 03:44 AM | Calgary | -1.1°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
North

Inuvik to Tuktoyaktuk highway construction to resume in January

Mild winter weather so far in N.W.T means the third season of work on the Inuvik to Tuktoyaktuk Highway likely won't begin until the new year, say contractors.

Mild weather nixes early start this year for gravel hauling

Crews work on the Tuktoyaktuk end of the Inuvik to Tuk all-weather road. (James MacKenzie/Department of Transportation)

Mild winter weather so far in N.W.Tmeans the third season of work on theInuvik toTuktoyaktuk Highway likely won't begin until the new year, say contractors.

"It all depends on the weather and the ice right now," saidKurtWainman, owner ofNorthwind Industries, one of two contractors on the project.

Although gravel hauls haven't started yet, Wainmansaid hehas a crew of about 20 building an ice road to a gravel pit that's located about 14 kilometres from Inuvik along the portion of the highway that has already been constructed.

"We are preparing the ice to haul on. We've been flooding for two weeks and we'll be going for another two weeks," Wainman said.

When completed, the two-lane gravel highway will run137kilometres from Inuvik to Tuktoyaktuk. Construction is expected to cost$299 million.

About 150 people work on the project each yearduring the winter months.

The Tuktoyaktuk contractor, E. Gruben's Transportation Ltd., says its crews have also begun building ice roads to access its gravel pits on the northern endof the road.

Last year both contractors hauled enough gravel to fill more than 150 Olympic-sized swimming pools beforethe end of December.

Building ice bridges strong enough to support the haul trucks dependon cold weather consistently below 20 C, or even better, 30 C, Wainmansaid.

"To me the biggest challenge is climate change. It's just such a drastic change," saidMervenGruben, vice-president of E.Gruben'sTransportation.

Lack of snow, needed for building ice bridges and ramps, is also a problem forTuktoyaktukcrews, said Gruben.

"Last year we started earlier, we were usingsnowmakers,"Grubensaid.

"That proved to cost us a lot of money and that didn't get us too farahead. This year we are just going to wait it out."

Despite these challenges, both contractors say the highway will be completed on schedule by fall 2017/winter 2018.

Gruben saidthe highway will be completed, even if they have to "haul like hell."

The Department of Transportation has not responded to CBC's request for comment but it has said recently the project will be completed within the $299 million budget.