'Milestone' hit as wind turbine arrives in Inuvik, but project now more than $20M over budget

It wasn't easy delivering asingle 3.5-megawatt wind turbine with blades that each span the width of a football field. But, with the help of three barges, the equipment has begun arrivingin Inuvik, N.W.T

Infrastructure Canada looking at how to help with cost overrun

Parts of the wind turbine arrived in Inuvik, N.W.T., on the evening of Sept. 20. (Karli Zschogner/CBC)

It wasn't easy delivering asingle 3.5-megawatt wind turbine with blades that at 67 metres span more than the width of a football field butwith the help of three barges, the parts began to arrive in Inuvik, N.W.T., on Tuesday.

It was done without damage, said the Northwest Territories government, callingit a"milestone" feat, even thoughthe project and the shipping itself wasdelayed forvarious reasons.

"It's not like we're driving a transport truck down the major highway," said Steve Hagerman, director of Marine Transportation Services in Hay River.

Hagerman said "considerable groundwork" was done at the terminal in Inuvik last monthto make sure it was level, among other "enhancements" to prepare for the barges.

The turbine is part of the Inuvik Wind Project, which officials hope will reduce the amount of diesel needed for power in the community by 30 per cent. That would offsetdiesel consumption in Inuvik, the N.W.T.'s largest diesel-powered community, by threemillion litres annually, the territory said.

Tony Coleman, who's into his 12th season of being a deckhand, said he's never witnessed such a large delivery.

A portrait of a man at a shipping port.
Tony Coleman, a deckhand for the Marine Transportation Services barge, helped with the transportation of a wind turbine to Inuvik, N.W.T. (Karli Zschogner/CBC)

"This is the biggest I've ever seen," he said. "We've had big fuel tanks and everything we've taken to DEW line sites, but I've never seen anything like this take up the full length of the barge [and] it's sticking out over too."

Construction of the project began in January 2022, and the turbine is expected to be operational by early 2023.

Putting it together involves theinstallation of the turbine and a small battery storage system, a six-kilometre access roadand a distribution line connecting it to existing lines near Inuvik's Mike Zubko Airport.

Cost for turbine well over budget

On top of delays, the cost to build theaccess road, costs for cranes to move and assemble the turbineand the cost of the battery storage system are all higher than anticipated.

The Northwest Territories Power Corporation (NTPC), which is responsible for the project through its sister company NT Energy,says it might cost between $20 and $30 million extra.

Part of the added costs are for the access road, the bid for whichcame in$2.1 million more than was estimated in the original budget, according to Doug Prendergast, NTPC's manager of communications. The access road contract is about15 per centof the project total.

Prendergast said part of the reason for higher costs is because of inflation and ongoing global supply chain issues caused by COVID-19-related lockdowns around the world.

One of three barges in Inuvik, N.W.T., delivers parts for a wind turbine. (Karli Zschonger/CBC)

While the turbine itself did not cost extra, as it was purchased before the pandemic, Prendergast saidthere's a host of other elements for the project that did.

"While final budget costs can't be determined until the project is completed, the current estimated budget is in the $60- to $70-million range," said Prendergast.

The original budget was approximately $40 million.

The territory has reached out toInfrastructure Canada about theproject funding shortfall, and the territory "will be following up to discuss this issue, in an effort to help alleviate project cost escalations," Prendergast said.

In 2018, the project became the first of its kind in the N.W.T. to get funds from the Investing in Canada Infrastructure Program, according to the territory. The federal government previously announced it's putting up to $30 million toward the project, while the territorial government is contributing$10 million.

It's not clear who will cover the substantial increase needed to finish the project.

In an email, InfrastructureCanada confirmed it'sawarethatInuvik's wind projectis facingcost increases.The department said it is currentlyreviewing information submitted bytheN.W.T. government"toseehowitcan be addressed within theparameters of the Arctic Energy Fund."

Road construction, then assembly

For now, the turbine blades and other components will be stored at the Marine Transportation Services (MTS) facility in Inuvik, while work continuesonthe access road right now about 50 per cent complete and set to open in November and at thesite.

The territory said other materials are on site and installation has begun,while work is still being done on theturbine's foundation.

Eventually, the blades and other parts will be taken to their finaldestination, about12 kilometres down the DempsterHighway and then another fivekilometres up a winding road.

With files from Karli Zschogner