Home | WebMail | Register or Login

      Calgary | Regions | Local Traffic Report | Advertise on Action News | Contact

Sign Up

Sign Up

Please fill this form to create an account.

Already have an account? Login here.

North

Dominion Diamond Corp. says Ekati mine expansion on track

Despite a concerted effort to trim costs at all of its operations, Dominion Diamond Corporation says it still plans to start building a new pit at its Ekati diamond mine next year.

Dominion expects to start building Jay expansion in 2016, have it in production by 2021

Dominion Diamond Corporation announced last week that construction on the Jay expansion to its Ekati diamond mine is on track to begin in late 2016. (Dominion Diamond Corporation )

Despite a concerted effort to trim costs at all of its operations, Dominion Diamond Corporation says it still plans to start building a new pit at its Ekati diamond mine next year.

The pit, called Jay, could help the mine stay in production until 2033.

The construction update, given by Dominion officials last week during a conference call, came a week after another N.W.T. diamond producer, De Beers, announced it's mothballing the Snap Lake mine because of a downturn in the diamond market.

"It wouldn't surprise you to know that we are reviewing our cost structure, looking at all of our capital sustaining and development capital to make sure that we are only spending money we absolutely have to," said Dominion CEO Brendan Bell during the earnings call.

Dominion, which also owns aminority stake in the Diavik diamond mine, has cancelled diamond exploration drilling it had planned to do near Ekati in 2016.

It's also looking to trim operational costs at the current Ekati mine, negotiating deals with fuel suppliers so that it only has to start paying for delivered fuel once it starts burning it.

"We know that we need to get to a sustainable lower cost base to make future projects like Jay as profitable as possible," said Bell.

Dominion still plans to begin building Jay as soon as it has the permits it needs, says Bell.

What's the holdup, then?

The project's environmental assessment is due to wrap up soon, with the Mackenzie Valley Environmental Impact Review Board expected to provide its yay-or-nay recommendation in January.

That recommendation will then need to be rubber-stamped by the N.W.T.'s minister of lands, who still needs to be named by Premier Bob McLeod.

Then provided the minister OKs the project the Wek'eezhii Land and Water Board will issue the permits Dominion needs to start building Jay.

Dominion expects that to happen toward the end of 2016, with production at Jay beginning in 2021.

Corrections

  • A previous version of this story incorrectly stated which N.W.T. minister approves reports of environmental assessment.
    Dec 17, 2015 7:05 PM CT