Mackenzie pipeline report OK'd by N.W.T., Ottawa - Action News
Home WebMail Saturday, November 23, 2024, 03:42 AM | Calgary | -11.7°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
North

Mackenzie pipeline report OK'd by N.W.T., Ottawa

The proposed $16.2-billion Mackenzie Valley gas pipeline is a step closer to reality after the federal and N.W.T. governments agreed Monday with most of the recommendations set out by a review panel last year.

The proposed $16.2-billion Mackenzie Valley gas pipeline isa step closer to reality after the federal and Northwest Territories governmentsagreed Monday with most of therecommendations set out by a review panel last year.

Theysaidthey can eliminate or mitigate any potential adverse impacts if the1,200-kilometre natural gas pipelinegoesahead.

"Should the [project] proceed, it will do so within a responsible environmental stewardship framework," federal Environment Minister John Baird said in a release.

The two governments released their final responsesto a report by the Joint Review Panel, which spent five years studying the proposal by a consortium of companies led by Imperial Oil to build the pipeline from the Beaufort Sea through the Northwest Territories to existing networks in Alberta.

Released in December 2009, thepanel's report came with 176 recommendations most of which were directed at the federal and N.W.T. governments to mitigate any adverse environmental, economic and social impacts the project may have.

On Monday, both governments said they accept the intent of "a vast majority" of the panel's recommendations aimed at them. Somerecommendations were not accepted because they were deemed to be outside thepanel's mandate.

Thepipeline planisstill being reviewed by the National Energy Board, a federal body that regulates parts of Canada's energy sector.

The NEB's decision on whether to approve the project is expected before the end of this year. Imperial Oil has said it won't make a final decision on whether to proceed until 2013.

"An unprecedented level of public consultation was undertaken prior to finalizing the governments' response, which highlights our commitment to implementing the appropriate mitigation measures to protect the environment and address the social, cultural and economic impacts associated with the proposed project," Baird said.