Mackenzie Valley Highway: A dream that is proving difficult to realize - Action News
Home WebMail Sunday, November 10, 2024, 09:49 PM | Calgary | 0.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
North

Mackenzie Valley Highway: A dream that is proving difficult to realize

The Northwest Territories government says it is moving ahead with the Mackenzie Valley Highway project, but so far its a project that seems to remain just over the horizon.

Highway may open in 2030, according to latest gov't predictions presented for mega project

A vehicle is seen stopped on a snow-covered road.
A file photo of the Mackenzie Valley Winter Road between Norman Wells and Fort Good Hope, N.W.T., in March. The N.W.T. government says it's moving ahead with the Mackenzie Valley all-season highway, but so far it's a project that seems to remain just over the horizon. (John Last/CBC)

The Northwest Territories government says it is moving ahead with the Mackenzie Valley Highway project, but so far it's a project that seems to remain just over the horizon.

The highway has been talked about for decades. Hopes were raised in 2013, when the territorial government filed applications for the land and water licences it needed to build the $1.67 billion, two-lane gravel road.

But 18 months later, the government shortened the highway by more than half to reduce the cost.

Instead of linking up to the Dempster Highway, it would end 321 kilometres from Wrigley, at Norman Wells, and cost $700 million.

The change sent the regulatory agency doing the environmental assessment, and all of the parties involved in it, back to the drawing board for six months to develop new terms of reference for the assessment.

People are very supportive of the project in general and anxious to see it proceed.- Sonya Saunders, Infrastructure Department director

The revised project description included an estimated timeline to see the project through to completion: "Subject to regulatory approval and confirmation of federal funding, construction could start in mid-2017 and continue to 2022."

Then the territorial government told the review board, it needs to pause the environmental assessment process. More time was needed to complete a detailed project description that would form the basis of the environmental assessment. That was about three and a half years ago.

"Really it's been about funding and being able to get the money to proceed," said Sonya Saunders, director of strategic planning for the N.W.T. Department of Infrastructure.

"Getting through the environmental assessment process itself is very expensive."

The government shortened the highway by more than half to reduce the cost. Instead of linking up to the Dempster Highway, like pictured here, the highway would end at Norman Wells. (CBC)

The territorial government got that money last year. The federal government agreed to put in $102.5 million together with a territorial government contribution of $37.5 million. In addition to paying for the environmental assessment, the money was to be used for planning and construction of a bridge over the Great Bear River and a 15 kilometre stretch of road north of Wrigley.

In meetings the department has been hosting in Norman Wells, Tulita and Wrigley the past year, the department has said it has spent $145 million on the project since 2000. It laid out how the new money will affect the timeline for the project. It also got feedback on progress so far.

"I think in the Sahtu, the concern we're hearing overwhelmingly is just the length of time it takes to get through the environmental regulatory process," said Saunders.

"People are very supportive of the project in general and anxious to see it proceed."

Saunders added people were looking forward to seejob opportunities with the construction of the road, and what the road will bring to that area of the territory.

Construction predicted to start in 2024

Under the estimated timeline presentedat those meetings, construction of the highway won't begin for almost another five years, in Sept. 2024.

The timeline estimates six and a half years for construction, though Saunders says it is difficult to say at this point how long it will take to build.

If it does take as long as estimated, the road would open in 2030.

Meeting even that lengthy timeline will depend on solving the same problem that has delayed the project so far finding the money to build it.

Saunders said the federal government has proven more likely to so-called "shovel ready" projects, those that have all the required regulatory approvals.