Nanisivik naval refuelling facility in Nunavut on track and on budget for fall 2018 opening - Action News
Home WebMail Tuesday, November 26, 2024, 01:05 PM | Calgary | -8.3°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
North

Nanisivik naval refuelling facility in Nunavut on track and on budget for fall 2018 opening

The $130 million refurbishment project will create an Arctic port used mainly as a refueling point for vessels from the Canadian navy and Canadian Coast Guard.

$130 million Arctic port will only be staffed during the navigable season, August to October

Re-bar will provide reinforcement in the concrete that will be poured for the new surface of the jetty at the Nanisivik Naval Facility on northern Baffin Island. (Department of National Defence)

Roofs are being welded onto two giant fuel tanks at the Nanisivik naval facility under construction near Arctic Bay, Nunavut.

The refuelling station will enter the home stretch of construction this summer, with final checks occurring next summer before it becomes operational in the fall of 2018.

"Much of the infrastructure will be near complete within the next month and a half and we expect that commissioning activities, that means our tests and trials, will begin," said Rod Watson, project manager for the facility.

The project budget is $130 million and Watson expects the port to come in on budget and on time for the revised 2018 deadline.
Fuel tanks under construction. (Department of National Defence)

Each of the two fuel tanks is designed to hold 3.75 million litres and a pipeline has been built to run from the tanks directly down to the jetty.

There will be an unheated storage facility and a small office, but the port will only be staffed during the navigable season, which Watson estimates is from the beginning of August until October.

Initially slated for completion in 2015, Watson said they realized the short summer window for construction would delay the project.

Environmental and geotechnical studies needed to be done before construction could begin and he said the team had difficulty getting the necessary equipment to the northern location.
A map showing the location of the planned Nanisivik Arctic naval facility. (Canadian Press)

The project was also scaled back from the plans announced in 2007 by Stephen Harper in his "use it or lose it' speech about Arctic sovereignty due to high construction costs.

Now, the facility will be mainly a refueling point for vessels from the Canadian navy and Canadian Coast Guard.

Watson says the coast guard has used this facility for years as it marshalls cargo vessels through Strathcona Sound and he expects they will continue to do so.

The original Nanisivik port was part of a lead and zinc mine that closed in 2002. While the buildings and fuel farm that were there have been removed, the jetty will look much the same.

The construction crew is currently pouring concrete to resurface the area.

Around 60 crew are on-site this summer, 11 of whom are local hires.
The general use storage building shown under construction. (Department of National Defence)

"We've worked very hard to make sure people from the community are involved and are hired to work at the site and we expect to continue that as we move from construction into operation," Watson said.

Operational staff will help with the refueling of some of the Arctic patrol vessels that the new liberal defence policy promised to deliver.

The first of which will be delivered in 2018, though that doesn't necessarily mean it will make it north to Nanisivik next year.