N.W.T. MLAs get glimpse of future remediation work, and question how northerners will benefit - Action News
Home WebMail Friday, November 22, 2024, 01:35 PM | Calgary | -10.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
North

N.W.T. MLAs get glimpse of future remediation work, and question how northerners will benefit

More than 500 sites in the N.W.T. are expected to need assessment, remediation or long-term monitoring in the future. But MLAs say theyre not convinced enough has been done to ensure northerners benefit from that work.

Remediation committee accused of not having clear goals or specific targets

A rocky ground with pools of water in the background has a tiny patch of fireweed growing in the foreground.
The Tundra Mine remediation site in the N.W.T. in 2018. There are more than 500 sites in the territory that may need to be assessed, remediated or monitored long-term in the coming years. (Jamie Malbeuf/CBC)

What will life look like in the Northwest Territories, after the mines?

There are more than 500 sites in the N.W.T. that may need to be assessed, remediated or monitored long-term in the coming years. The Remediation Co-ordination Committee, a joint effort between the federal and territorial governments, gave N.W.T. MLAs a look on Tuesday at what those efforts could mean for the territory's economy.

But MLAs questioned if enough is being done to make sure northerners get the most benefits possible from remediation efforts.

"I'm a bit concerned about the lag in doing all this work without actually getting people trained up and ready for these jobs in time to benefit from it," Katrina Nokleby, the Great Slave MLA, said.

A building with huge round stack on the ends sits on top of a hill with trees and orange dirt in the foreground.
The Giant Mine site near Yellowknife. (Chantal Dubuc/CBC)

The committee estimates that over the next 30 years, more than $4.8 billion will be spent on remediation in the N.W.T. That includes a $4.3-billion estimated cost for the cleanup of Giant Mine.

A 2022 report by the territorial government said the estimated 500 sites belong to the federal government, the territorial government and private companies. It said the largest remediation projects are related to resource extraction, but there isalso remediation workin communities, involving government projects and private enterprises.

Great Bear Lake, Rayrock, De Beers' Snap Lake mine and Giant Mine are already in the remediation process, according to the territorial government, with Rio Tinto's Diavik mine and De Beers' Gahcho Kue mine slated to start seeing remediation in the next decade.

There are three territorial departments working together for the remediation economy, including Industry, Tourism and Investment (ITI), Education, Culture and Employment (ECE), and Environment and Climate Change (ECC).

The overall goal is to make the most of the economic benefits that will come to the territory and communities, said Rasel Hossain, director of contaminants and remediation division in the N.W.T. region with Crown-Indigenous Relations and Northern Affairs Canada.

Hundreds of jobs, millions of dollars

The committee says itexpects remediation efforts to generate as many as 700 full-time jobs per year for approximately 15 years, with annual spending estimated at $291 million.

But Frame Lake MLA Kevin O'Reilly questioned if there were any specific targets around employment and spending.

"I don't sense there is a clear set of goals, objectives or targets," O'Reilly said during Tuesday'smeeting.

A man sits at his desk holding a pen and paper.
Frame Lake MLA Kevin O'Reilly. (Travis Burke/CBC)

Kam Lake MLA Caitlin Cleveland echoed O'Reilly's comments, asking the committee if they would be able to track how much money leavesthe territory and why.

Menzie McEachern, assistant deputy minister with mineral and petroleum resources in the Industry, Tourism and Investment (ITI) department, said tracking contracts and workers is something that is possible and has been done already with the Giant Mine remediation project, noting it is "quite a lot of work."

"It is definitely something we can look at," McEachern said.

Taking aim at the numbers presented, O'Reilly said he thought the committee "significantly underestimated the opportunities" with all the sites in the territory.

But McEachern said estimating costs for these projects is an "evergreen process."

"There is not going to be a perfect answer at any moment in time," McEachern said.

Planning initiative continues

The committee is working with the federal government under what is called a strategic planning initiative. Thecollaboration involveda phase of analyzing economic opportunitieswith remediation and monitoring, and a second phase involving more analysis and a "Have Your Say" survey conducted through the territorial government.

The committee that presented Tuesday is the third phase.

Dozens of rusty barrels sit together with trees in the background.
In this file photo, a number of barrels gather rust at the Norex Mine site near Great Bear Lake. (Deline Land Corporation)

Skills development and business capacity were highlighted as initiatives underway. That means Aurora College plans to launch two training programs, and efforts are underway to fund Indigenous participation in major remediation opportunities.

About 40 per cent of the jobs expected to be created will require post-secondary skills or training.The committee noted that many of the labour market needs of remediation already mirror those of the mining and infrastructure sectors, including environmental sciences, heavy equipment operations, and administrative and project management support.