Termination notices sent to over 1,100 Baffinland employees on Sunday - Action News
Home WebMail Thursday, November 14, 2024, 11:51 AM | Calgary | 6.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
North

Termination notices sent to over 1,100 Baffinland employees on Sunday

Baffinland spokesperson Peter Akman said the company is preparing fortwo rounds of terminations to take effect if the company does not receive permission to continue extracting six million tonnes of iron ore annually from the Mary River mine.

In the event of terminations, there will be 2 rounds; Sept. 25 and Oct. 11

Baffinland's Milne Inlet operations, pictured in January 2021. A company spokesperson says the company is preparing fortwo rounds of terminations to take effect this fall. (Nick Murray/CBC)

BaffinlandIron Mines sent termination notices to over 1,100 of its staff on Sunday, including 200 Inuit employees.

Baffinland spokesperson Peter Akman said the company is preparing fortwo rounds of terminations to take effect on Sept. 25 and Oct. 11 if the company does not receive permission to continue extracting six million tonnes of iron ore annually from the Mary River mine.

Akman said the noticesaffectall employees in anyaspectof the company's northernoperations.

"Anyone who's working at the two sites, the port or the Mary River site, but also across Iqaluit, and across Nunavut ... Anyone who is working for us, will have potentially received the notices."

One of the employee letters, obtained by CBC News, explains the termination notice is a result of the regulatory process moving "more slowlythan is necessary to meet Baffinland's operational requirements."

"As a result, pursuant to section 14.03(2) of the [Nunavut Labour Standards]Act, as of the date of this letter, you are being provided notice that on the 25th day of September 2022, your employment with Baffinland will be terminated," the letter reads.

The Nunavut Impact Review Board (NIRB) is currently reviewing arequest from the company to carry on extracting ore at asimilar rate as recent years, while the federal minister ponders what to do with the NIRB'srecommendation that the mine not be allowed to expand as planned.

The minister of Northern Affairs, Dan Vandal, has urged the board to make its recommendation by Aug. 26. In a notice July 19, NIRB said it would be unable to meet that timeline "due to logistical constraints and existing board commitments."

Baffinland saidthe deadline of its production increase extension was meant to fall after the Phase 2 regulatory process was completed, butdue to "a number of factors, including the COVID-19 pandemic, the authorization expired before the process concluded."

Intervenor group Oceans North has previously stated that Baffinland's situationis"a foreseeable consequence of poor management and planning," and expressed concern that the company is using the prospect of layoffs to pressure the Nunavut Impact Review Board "to approve current and future expansion of the mine."

Akman said the company is still working on getting its permit to increase its limits to six million tonnes per year, and if it is successful, then Baffinland will rescind the termination notices.

In the meantime, Akmansaid the letters were sent to employees last weekend "out of an abundance of caution" in the event that mine operations aren'tapproved by the time it meets its currentproductionlimit. Heexpects the company will reach that limit on the ore extraction sideby mid-September, and on the shipping side by early October.

When that happens, and if no approval comes before then, Akman saidthe company will have "no choice" but to stop production.

"Once we reach that amount, then we have to stop," he said. "For the remainder of 2022 we will have no more work to do."

Akman didn't say whether the employees who could be terminated would be re-hired again.

With files from Jacqueline McKay