'Large tension crack' threatens major sewer line in Whitehorse - Action News
Home WebMail Saturday, November 23, 2024, 01:47 AM | Calgary | -11.7°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
North

'Large tension crack' threatens major sewer line in Whitehorse

Whitehorse city officials say a "large tension crack" on the escarpment threatens to damage one of the city's main sewer lines. City staff are proposing a $10-million fix.

'High probability of imminent slope failure that will damage or destroy' sewer line in next year, report says

An overhead view of a manhole on a treed slope, with a large crack in the soil.
A photo taken from a drone in June 2022 shows a manhole near a large tension crack on Whitehorse's escarpment. City officials say the crack is expected to eventually cause a slide, and that threatens one of the city's main sewer lines. (City of Whitehorse)

Whitehorse city officials say one of the city's main sewer lines is at risk from a probablelandslide, maybe eventhis year and it's a$10-million fix to avoid a potential "uncontrolled release" of raw sewage.

City engineers say a "large tension crack" was discovered last spring along the Takhinisanitary trunk line, which carries nearly half of the city's raw sewage to the Marwell lift station. The crack isjust east of the Pepsi Softball Centre on Range Road,on a relatively steep section of the escarpment.

It's similar to other cracks that were seen elsewhere along the escarpment before aseries of landslides last spring.

"Based on the hazard and risk assessment completed by the City's geotechnical engineering consultants, there is a high probability of imminent slope failure that will damage or destroy this portion of the main within the next year," reads an analysis presented at a city committee meeting on Monday.

Speaking at a news conference on Tuesday, Gareth Earl, the city's associate manager ofengineering services, said aslide is "highly probable."

"So we're doing our due diligence to prepare for that."

A view looking down on a small city from a forested slope in winter.
A view from the top of the escarpment in Whitehorse, near the area where a tension crack threatens one of the city's main sewer lines. (Paul Tukker/CBC)

The steel-pipe sewer line at risk was installed in 1975 and it carries raw sewage to the Marwell lift station from an area including the residential neighbourhoods of Takhini, McIntyre, Arkell, Ingram, Copper Ridge, and Granger, as well as Yukon University, the Canada Games Centre and the Whitehorse Correctional Centre. Earl says it carries about 40 to 50 per cent of the city's sewage, at a rate of about 150 to 200 litres per second, "roughly equivalent to like, 1,000 kitchen taps left on."

The plan is to construct a new sewer main around the potential landslide area later this year. City council is being asked to approve the $10-million budget so a tender can go out next month, and work can begin this spring.

The design includes approximately 1.2 kilometres of sewer line that would go along Range Road and then down a more gentle slope to Marwell.

Inthe meantime, city engineers have designed a temporary bypass that will be used once the spring melt begins, likely in April. The bypass involves an above-ground pipe and will be used until the new main is operational.

Some construction fencing is seen at the edge of a snowy, treed slope with a city visible in the distance.
The plan is to construct a new sewer main around the potential landslide area later this year. (Paul Tukker/CBC)

The city also dug a sump at the bottom of the slope last year to collect any sewage in case of a spill.

Several landslides in 2022

Whitehorse's escarpment was under the microscope last spring after several landslides during thespring melt. One largelandslideblocked offone of the main thoroughfares into downtown for several weeks.

The tension crack that threatens the Takhini sewer main was discovered last June. It was not there during an inspection a year earlier, city officials say.

City council last summerapproved $350,000 to immediately begin work on a solution for the sewer main. Now council is being asked to findanother $9.75 million to complete the work.

The project would go out for tender next month, and work is expected to begin by May and be done before the end of 2023.

In the meantime, Earl said engineers will continue to monitor the tension crack and the sewage flow for any change.

With files from Meribeth Deen