Yukon prospector, contractor each fined $1,200 for cutting illegal trail

Nicolai Goeppel built a 17-kilometre trail north of Carmacks last year without a permit. He's been fined $1,200 under Yukon land use regulations.

Nicolai Goeppel's company bulldozed a 17-kilometre trail north of Carmacks without permits

The 17-kilometre trail is indicated on this map by a blue line. The North Klondike Highway is the orange line at left, and Nicolai Goeppel's prospecting lease is the yellow block at top right. (Government of Yukon)

A Yukon prospector, and a local contractor,will each pay $1,200 forbuilding a 17-kilometre trailwithout permits.

The fines were delivered in YukonTerritorial Court on Wednesday.

Prospector NicolaiGoeppelpleaded guilty to three charges under Yukon land useregulations. The trail was built last summer near McGregor Creek,about 45 kilometres north of Carmacks.

H.Coyne and Sons, the excavating contractor that did the work, also pleaded guilty to three chargesunder territorial land use regulations.

The government says the trail isabout 3.5 metres wide andleadstoa remote prospecting lease that was still pending approval. Most of the trailwas cut through Crown land.

"This is one of the worst offences Yukon has seen in terms of contraventions of land use in recent years," said Crown prosecutor MeganSeiling.

Judge PeterChilsolmsaid the trail"far exceeded the area where Mr.Goeppel had staked," but acknowledged thatGoeppelhadshown remorse bycontacting the Little Salmon/CarmacksFirst Nation to apologize, and hadcooperated with law enforcement.

The trail was never subject to an environmental assessment before being built and was discovered by a local trapper.

Defence blames 'lack of clarity' and government delays

Goeppel'slawyer, Richard Fowler,argued the case was due to a "lack of clarity," and not a disregard for rules.

Fowler described a mining culture in Yukon where miners sometimes start work based on informal promises.

"Work was encouraged to begin before permits were issued, because of delays in issuing permits. That's because the work season is short," he said.

He told the judge that work was done based on informal assurance from the region's mining recorder.

"This is not an individual who just blindly went and built a road. He was in frequent contact with the mining recorder. Mr. Goeppel believed what he was doing was OK," Fowler said.

Crown prosecutors had argued for the maximum allowable fineunder territorial land use regulations, which would have been $1,500 ($500 each, for thethree charges), but Fowler argued that would have been excessive.

Environmental damage, First Nation says

The Little Salmon/CarmacksFirst Nation had complained thatthe trailinterfered with atrapline,and caused environmental damage.

On Wednesday, the Crown soughtto have a Natural Resources Officer testify to describe environmental damage, but the court denied the request.

The lawyer for H. Coyne and Sons, meanwhile,argued that thecompany did the work in good faith, believing permits had been granted to Goeppel.

But the judge found the company had an obligation to "verify the work was lawful."

Goeppel and the company will eachpay a $180 victim surcharge as well.