MacKay Bridge delays, Macdonald closure cause weekend traffic pain - Action News
Home WebMail Saturday, November 23, 2024, 03:41 PM | Calgary | -11.6°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Nova Scotia

MacKay Bridge delays, Macdonald closure cause weekend traffic pain

The bridge commission is promising that kind of weekend backup will not happen again in the foreseeable future.

Halifax Harbour Bridges says there should not be a repeat of this past weekend's delays

The Big Lift in progress on the Macdonald Bridge. (Submitted by Halifax Harbour Bridges)

Drivers trying to cross Halifax Harbour over the weekend facedsignificant delays due to MacKay Bridgeconstruction work and the closure of the Macdonald Bridge.

The bridge commission is promising that kindof weekend backupwill not happen again in the foreseeable future.

The Macdonald Bridge was closed over the weekend as part of the Big Lift redecking project. A team from the contractor American Bridge was working on the structure.

Also on Saturday, lanes on the MacKay Bridge ramp had to be reduced due to an unrelated construction project.

A recent inspection of the MacKay found rust on the underside of the Windsor/Robie exit ramp on the Halifax side. The bridge commission said the ramp was still safe, but needed repairs as soon as possible.

Work had to be done on ramp

Alison MacDonald, a spokesperson for Halifax Harbour Bridges, said the bridge commission apologized for the delays but the work had to be done during daylight hours, because it involved concrete setting at particular temperatures.

She said closing the Macdonald at the same time was unavoidable due to the Big Lift work, but that the work on the MacKay was completely finishedand there will not be a repeat of the past weekend.

The contractor on the Big Lift project had originally planned to raise the 31st deck segment this past weekend.

However, the team said it needed more time to get familiar with a new deck-fitting process and the segment will instead be inserted during the coming weekend.

Big Lift continues

The remaining deck segments to be fitted are those closest to the Halifax side, over the navy shipyards.

Those segments are being fitted using a different process than previous segments. They won't be lifted from a barge in the harbour, but are lifted from the ground.

MacDonald said after the 31st segment, the team will replace two or three segments per weekend.

The project is still considered on track to finish fitting all segments by the end of 2016.