City followed rules in awarding LRT contract to SNC-Lavalin: auditor - Action News
Home WebMail Tuesday, November 26, 2024, 10:08 AM | Calgary | -16.2°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

City followed rules in awarding LRT contract to SNC-Lavalin: auditor

Senior city staff followed the rules "to the letter" when they pickedSNC-Lavalinas winner ofthe $1.6-billion contract to extend Ottawa'sTrillium Lineeven though the engineering giant had twice failed to meet the technical threshold for the project, the city's auditor generalhas found.

Investigation launched after CBC reported firm failed to meet technical score for $1.6B Stage 2 contract

Ken Hughes, Ottawa's auditor general, addresses the city's audit committee on Tuesday, Nov. 26, 2019. (Jean Delisle/CBC)

Senior city staff followed the rules "to the letter" when they pickedSNC-Lavalinas winner ofthe $1.6-billion contract to extend Ottawa'sTrillium Lineeven though the engineering giant had twice failed to meet the technical threshold for the project, the city's auditor generalhas found.

"The job of the auditor general is to say what we found, not what someone wanted us to find," Ken Hughes told councillors Tuesday afternoon. "What we found is that the process was followed to the letter."

However,Hughes recommended the city make its procurement process clearer in the future, including making the language in the request for proposals (RFP) public.

Hughesnoted council had delegated the authority for the entire procurement process for LRT Stage 2 to city staff, requiring only that they come back with a recommendation. In taking that route, council appearsto have delegated away its right to demand information on the process, he said.

In future, the auditor general said, council may want to demand staff report back more frequently, andmake it clear what information can be shared"to avoid misunderstanding."

"For any request for proposals for large projects, the city has to increase the transparency," Hughes told reporters after the meeting.

Audit launched after CBC story

CBC first reportedback in March that, according to sources,the troubled Montreal-based engineering company had failed to score 70 per cent on the technical evaluations, but still wonthe contract to extend the north-south rail line.

At the time, the city refused to confirm whether that was the case. City officials also refused to say whether there was any language in the contract that would allow a finalist to progress throughthe procurement process despite failing tomake the minimum grade.

SNC-Lavalin Group Inc. won the $1.6-billion contract for the Trillium Line extension despite twice failing to meet the minimum technical grade. (Paul Chiasson/Canadian Press)

But in August, the city finally admitted that SNC-Lavalinfailed to score the minimum 70 per cent requirement not just once, buttwice.

At the time, city manager Steve Kanellakosalso revealed that theRFPprovided the city with the "sole discretion"to move a proponent along in the bidding process, even if it hadn't metthe minimum grade information that council didn't have back in March when it approved SNC-Lavalin'scontract.

Discretionary clause a surprise

On Wednesday, Hughes told councillorsthe sort of discretionary clausethe city used to wave SNC-Lavalin through the bidding process is common in contracts of this size.

And yet, despite having been a senior bureaucrat for years, Hughes said he'd never heard of this sort of discretionary power.

"I was surprised to hear that there was discretion clause," he said.

"That alone didn't negate the allegations that were being made, but it certainly meant that the bulk of the allegations that were being made were groundless because there was this discretion clause."

I would not have ever voted in favour of this project knowing that the winning proponent failed the technical requirement.- Coun. Catherine McKenney

But some councillorsfound no comfort in the knowledgethe rules had been followed.

"I would not have ever voted in favour of this project knowing that the winning proponent failed the technical requirement," said Coun. Catherine McKenney, who voted in favour of the contract back in March. "We can massage that nuance in any way we want, but I would have never, ever voted to approve that."

An Alstom LINT train pulls into Bayview station on the Trillium Line earlier this year. (Chris Rands/CBC)

Coun. Jeff Leiper argued council should have been told the discretionary power existed and was used, which would have allowed elected officials to ask more probing questions.

"It makes me feel a little tight my stomach," Coun. Theresa Kavanagh said ofthe realization that she'd voted on the huge contract without all the facts.

"I think that it would have been important to have a lot of this information available," she said. "It seems that the bottom line in this is that regardless of the technical scores,it's about the lowest bid wins and the bid."