Home | WebMail |

      Calgary | Regions | Local Traffic Report | Advertise on Action News | Contact

Ottawa

Rideau Street sinkhole floods 300 metres of LRT tunnel

Engeineers say 300 metres of light rail tunnel are flooded after Wednesday morning's Rideau Street sinkhole and water main break.

First look inside tunnel that crews had to abandon 50 metres shy of finishing their dig

Concrete poured into the sinkhole nearly reached the top Thursday. About five storeys below, engineers are set to determine what damage was caused to the LRT tunnel. (Mathieu Fleury/Twitter)

Engineering experts say 300 metres of the city's light rail tunnel isflooded after Wednesday morning's Rideau Street sinkhole and water main break.

A piece of construction equipment is dredged from the Rideau Street sinkhole on Friday, June 10, 2016. (Mathieu Fleury/Twitter)

Engineers for the Rideau Transit Group (RTG)went down into the tunnel Friday to assess the damage for the first time since workers were told to drop their tools and leave the site in the minutes after the street above the tunnel fell away, creating a sinkholefivemetresdeep.

Late Friday afternoon, City of Ottawa manager SteveKanellakos sent a memo saying they'd discovered the significant flooding.

"Over the next several days, water will be pumped out to allow teams to better assess the impact and plan the path forward," he said.

"RTGstaff are assessing conditions and finalizing a timeline for resuming tunneling work."

Kanellakosadded thatconstruction crews, despite the flooding, are back to work at the future Rideau Station.

He did not share details of how much water was in the flooded part of the tunnel.

RTG could be liable for costs

If work done for the LRT project ultimately caused the sinkhole, then RTG is liable to pay for the damage because of the nature of its public-privatepartnership (or P3) agreement with the city.

RTG ended up paying for the cost of repairing a 2014 sinkhole caused by LRT work on Waller Street near Laurier Avenue. The investigation into what caused the Rideau Street sinkhole is expected to take twice as long, according to Mayor Jim Watson. (Photo courtesy of City of Ottawa)

RTG was responsible for paying for the sinkhole damage that appeared at the corner of WallerStreetand LaurierAvenuein February 2014.

Ottawa Mayor Jim Watson said Thursday that this time it may take months to determinewhat caused the sinkhole.

"It took us about a month to do the Waller Street[sinkhole investigation]and this one is obviously substantially bigger," he said.

LRT tunneling almost complete

RTG had been digging the 2.5-kilometre light railtunnel from two ends, with bothmachines simultaneously moving toward each other.

The Rideau Station of Ottawa's light rail line will have entrances at the Williams Street pedestrian mall and in the northwest corner of the Rideau Centre. The yellow line depicts the platform. (City of Ottawa)

When the sinkhole opened upthe tunnel was almost complete, with the two ends now just 50 metres apart.

The westbound tunnel had made it to the futureRideau Station, which is also under construction but was notdamaged by the sinkhole, according to RTG technical manager PeterLauch.

"We're back working in the station itself," he said."It wasn't compromised. But on the tunnel, I can't tell you when we're going to start up again,it's going to take a while before we're back in there."

RTG working slow through unstable ground

Lauch said RTG understood they were working in unstable soil through the areaand crews were taking it slow.

This is what tunnel construction at the LRT's west portal looked like in 2014 near the future site of Lyon Station. The limestone there was much easier to bore through compared to the area beneath Rideau Street, according to RTG. (Waubgeshig Rice/CBC)

Rather than excavating at a pace of 4.5 to fivemetres a daythrough limestone, as crews didin the eastbound tunnel, the westbound workwas creeping along at 0.8 to onemetre a day.

CBC reported Thursday thatthe sinkhole occurred in the same place engineers conducting a geotechnical survey for the light rail project in 2011 discovered a 120-metre wide "bedrock valley" under Rideau Street.

The slow and steady approach will continue after repairs to get the tunnel back in the same shape it was before the sinkhole appeared, Lauch said.

LRT project expected to be finished on time

RTGCEO Antonio Estrada met with city manager Steve Kanellakos Thursday for the first time since the sinkhole appeared.Lauch said they discussednext moves forboth the sinkhole repairs and the LRT project.

Here's what the Rideau Station site looked like before construction began (top) and what it will look like when it's finished (bottom). Work on the station itself has not been stalled by the giant sinkhole. (Google Streetview/City of Ottawa)

Now that the sinkhole has been half filled with concrete, on Thursday night RTG began using "shotcrete" a kind of concrete that can be sprayed tostabilizethe vertical sides of the sinkhole soutility crewscanbegin reconnecting broken pipes.

By Friday afternoon, workers were back in the partially-filledpit.

As for the road closures on Rideau Street, Elgin Street and Sussex Drive, Kanellakos said they'll stay closed "until the full extent of the impact on surrounding infrastructure can be determined."

MoreRideau Street sidewalks are now open again, with north sidewalks only closed from Sussex Drive to the Tim Horton's entrance and south sidewalks from Sussex Drive to Nicholas Street.

Businesses that are still closed will reopen on a case-by-case basis when it's safe, the city said.

Lauch had said ThursdayRideau Street should be back in working order in two weeks.

The tunnel repairs, he said, should not take longer than a month.

RTG does not expect the repairs to delay the 2018 deadline for completing the LRT project.