No LRT by Canada Day, city confirms - Action News
Home WebMail Monday, November 11, 2024, 04:18 AM | Calgary | -1.3°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

No LRT by Canada Day, city confirms

Confederation Line builder Rideau Transit Group will miss afourth deadline tohand over Ottawa's light rail system.

Rideau Transit Group misses 4th deadline to hand over Confederation Line

Rideau Transit Group submitted paperwork claiming it was finished building Ottawa's new rail line and wanted to start final testing. The City of Ottawa, backed by an independent certifier, disagreed and said the consortium has work to do. (City of Ottawa)

Confederation Line builder Rideau Transit Group (RTG) will miss afourth deadline tohand over Ottawa's light rail system.

The LRT system will not be ready by June 30, city councillors on the finance and economic deveopment committee learned Tuesday morning.

Unfortunately, the vehicles are not ready for prime time.- John Manconi, transportation GM

There is nonew date set.

The Confederation Line was originally supposed to be ready byMay 2018, and RTG hadmissed two subsequent handover dates.

The problem remains the trains themselves, transportation general manager John Manconi told the committee.

"Unfortunately, the vehicles are not ready for prime time," Manconi said during Tuesday's update.

RTG and the city have agreed the 34 Alstom-built train vehicles need to be "virtually defect-free" and reliable, Manconi said, but the trains continue to experience problems with their doors and brake valves problemsthat are time-consuming to retrofit.

"We're not just sitting by and waiting for them," Manconi said, adding the city is bringing in high-priced experts to monitor the ongoing repairs.

Mayor Jim Watson also called Alstom CEO and president Henri Poupart-Lafarge on Tuesday.

"[I] let him know in no uncertain terms that we were fed up with his company's performance, and I'll send the same message to RTG," Watson said Tuesday.

Watson said Poupart-Lafargehas agreed to come to Ottawa from France to meet with officials from RTG and the city.

'The vehicles are not ready for prime time'

5 years ago
Duration 0:52
John Manconi, general manager of OC Transpo, says Rideau Transit Group will not be able to hand the LRT system over to the city by the end of June.

No new date

Manconi told the committee he's told RTGhe doesn't want the consortium to "give us a date just for the sake of giving us a date."

Because June 30 was not a formal contractual deadline, the city will not be levying a million-dollar penalty on RTG, as it has twice in the past, Manconi explained.

RTG has not received a payment from the city in months. The consortiumtried to submit paperwork a month ago to hit the important milestone known as "substantial completion,"whichtriggers a $59-million payment and allows it to launch a required 12-day trial run.

Fourth delay of LRT system 'not acceptable,' mayor says

5 years ago
Duration 0:40
Mayor Jim Watson says he's called a meeting with the heads of Rideau Transit Group and Alstom to discuss the delays and push for a solution.

'No grey zones'

Both the city and an independent certifier disagreed with RTG's assessment that it was finished, however, and met with RTG and rail experts to discussthe outstanding issues in detail.

Manconi confirmed Tuesdaythat the 12-day trial has not started.

"There's no grey zones. There's a comprehensive list. They know what they need to do," Manconi said.

Once the handover does happen, the city is supposed todeliver the final $202-million payment to RTG.

Manconihas said people will be able to ride the train some four weeks after that happens.

The city has been keeping track of the costs of the delays to keep extra buses on the road, for instance, and intends to deduct those from the final payment.

RTG disagrees, and Watson has said in the past he could see the dispute eventually landing in court.