City withholding millions from LRT builder - Action News
Home WebMail Monday, November 11, 2024, 01:06 AM | Calgary | -0.5°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

City withholding millions from LRT builder

OC Transpo general manager John Manconi says the city is currently paying Rideau Transit Group approximately one quarter of the total amount the LRT builder is seeking.

Rideau Transit Group, city in 'ongoing dispute' over payment deductions

A red and white public transit train on a track near a highrise.
An LRT train near Lees station on Ottawa's Confederation Line in May 2020. (Francis Ferland/CBC)

OC Transpo boss John Manconisays the city continues to withhold millions of dollars from Rideau Transit Group (RTG) over ongoing problems with Ottawa's new light rail system.

In a memo to the mayor, councillorsand transit commissioners Wednesday, Manconisaid the city has paid out approximately one-quarter of the amount RTG has billed in recent months.

Between October 2019 and July 2020, RTGsought approximately $60 million from the city, but Manconi saidfor now, the city will only be cutting a cheque for $17.45 million.

As reported by CBC, the contract with RTGallows the city to deduct payments for poor performance.

Manconi said the city is prepared to make partial payments for the period covering October 2019 to January 2020, as well asMay to July 2020. But payments for February to April 2020 period are on hold, since possible deductions have not yet been determined.

Those months saw "reductions in the availability of vehicles as a results of technical issues with wheel flats and arching issues," Manconi wrote.

'Ongoing dispute' over deductions

The city will only pay out $5.47 million for the October to January period, even though RTG invoiced $17.68 million.

"RTG and the city have been engaged in an ongoing dispute and discussion as to how work orders have been administered to date, and how they should be administered on a go-forward basis," Manconi wrote.

Seats on a train.
Rideau Transit Group has been unable to consistently provide 15 trains for service during peak periods, but has promised to do so by Sept. 8. (Jonathan Dupaul/CBC)

He said some progress had been made between the two parties in relation to certain "ambiguities" withthe project agreements, and discussions are ongoing.

There were some improvements made to the system between May and July because of reduced ridership during the pandemic. The city will pay out $11.97 million for those months, withholding only $683,000.

Cracked wheels sidelined trains

An additional $16 million is being withheld because the promised complement of 15 trains still isn't reliably available duringpeak periods.

"AlthoughRTG has recently been successful in running 15 double car trains, it cannot do so consistently due to the wheel cracking issue, which requires ongoing safety inspections," Manconi wrote.

Last month, CBC reported Canada's rail safety agency launched an investigationafter cracks were discovered in the wheels of several trains.

RTG has told the city 15 trains will be available during peak periods as of Sept. 8. If that happens, and the wheel crack issue has been resolved, the city could pay out an additional $16 million.

Add some good to your morning and evening.

More than the headlines. Subscribe to You Otta Know, the CBC Ottawa weekly newsletter.

...

The next issue of You Otta Know will soon be in your inbox.

Discover all CBC newsletters in theSubscription Centre.opens new window

This site is protected by reCAPTCHA and the Google Privacy Policy and Google Terms of Service apply.