LRT line to open Sept. 14 - Action News
Home WebMail Tuesday, November 26, 2024, 01:06 PM | Calgary | -8.3°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

LRT line to open Sept. 14

It may have arrived456 days late, but there's finally light at the end of the tunnel for people who've been waiting to ride Ottawa's new Confederation Line.

Mayor Jim Watson accepts symbolic key to $2.1B Confederation Line, thanks residents for patience

Take a ride on the Confederation Line

5 years ago
Duration 1:10
A timelapse of Ottawa's new LRT system, which runs between Blair and Tunney's Pasture stations.

It may have arrived456 days late, but there's finally light at the end of the tunnel for people who've been waiting to ride Ottawa's new Confederation Line.

The doors to Ottawa's$2.1-billion light rail system will open to the public on Saturday, Sept. 14, Mayor Jim Watson announced at City Hall Friday afternoon.

"This is truly an exciting day for the city of Ottawa, and I want to take an opportunity to thank the residents of our city for their patience," Watson said.

"The wait was necessary to ensure that we're bringing a safe, efficient and world-class transit system to our city one that will enhance Ottawa's position as one of the best places to live in the world."

Earlier on Friday, the mayor was joined by media, city officials,and dozens of politiciansfrom all three levels of governmenton an inaugural ride along the12.5-kilometre line, from Blair station in the east to Tunney's Pasture station in the west.

For most people on the train, it was the first time they'd travelled through the 2.5-kilometre tunnel under the downtown core.

"It's been hard not to smile the last couple of hours," Watson said. "It's been quite an exciting time."

Several people sit and talk while riding inside a train
Ottawa Mayor Jim Watson, centre, rides the Confederation Line with a number of other city officials and politicians on Aug. 23, 2019. (Joanne Chianello/CBC)

Taking keys to LRT

The city is expected to soontake control of the Confederation Line from Rideau Transit Group (RTG), the consortium led by SNC-Lavalin and ACSInfrastructure that, in December 2012, won the contract for Ottawa's biggest civic project in the city's history.

Michael Morgan, the city's director of rail operations, said while the citystill needscertain documents from RTG before that can happen,he doesn't expect that will affect the launch date.

Regardless, Watson was still handed a ceremonial key to the line Friday afternoon by RTG CEO Peter Lauch.

The city has always said it would need several weeks after the Confederation Line was handed over to prepare for the public launch of the system.On Friday, Watson said OC Transpo would now be carrying out "drills" in the days leading up to theofficial Sept. 14 launch.

Watson also acknowledged the serious traffic congestion residents have had to endure during the line's lengthier-than-expected construction.

"I want to reiterate my appreciation for their patience through this project," Watson said.

"I know the construction and its detour affected tens of thousands of residents, and my colleagues on city council heard from those residents both transit users and non-users alike."

A police officer stands next to the public art at Lyon station during the inaugural run of Ottawa's 12.5-kilometre Confederation light rail line on Aug. 23, 2019. (Joanne Chianello/CBC)

City to pay RTG $202M

Once that handover is complete, the city will make its final payment to RTG of $202 million. However, the city is expected to withhold an amount equal to its costs caused by the project's delay.

At last count, the city estimated that the LRT delay had cost the city $34.4 million, but because that calculation was based on a handover date of June 30, those costs are expected to be slightly higher.

RTGhas missed four official completion deadlines May 2018, November 2018, March 2019and August 2019 and will be penalized $1 million for each of the missed dates, the city has said.

Are you ready for rail?

5 years ago
Duration 1:12
The city has set Sept. 14 as the launch date for the Confederation Line?

'Safe and dependable'

Following Friday's announcement, city officials held a technical briefingto answer questions about what would still need to be done before theSept. 14 launch, as well as atrial run of the network that began July 29.

OC Transpo general manager John Manconi said there had been "a mixture of positive days and some challenging days" during the trial run, but thatRTG's trainsultimately achieved a 97 per cent trip success rate over nine days.

Manconialso said a specialist had been hired to deal with concerns over noise from the trainsnear Tunney's Pasture station.

No transit agency can claim perfection delivering a rail system. And we are no exception.- John Manconi

As for the 13 stations, Manconi said teams were out inspecting them daily and found that elevators, fare gates, ticket machines and train schedule displays were all working reliably.

All that essentially remained, he added, was a "deep clean" before the public launch.

"No transit agency can claim perfection delivering a rail system. And we are no exception," Manconi said. "But we promise the residents of Ottawa that staff will deliver a safe and dependable system."

Troy Charter, the city's director of transit operations, said there would now be more than 90 "operational drills" held over the next three weeks,including simulations of full and partially fulllight rail cars, as well as evacuation exercises, all designed"to ensure a seamless customer experience."

Once the Confederation Line opens, it's expected to run from 5 a.m until 1 a.m. from Monday to Thursday, 5 a.m. until 2 a.m. on Friday, 6 a.m. until 2 a.m. on Saturday, and 8 a.m. until 11 p.m. on Sunday.

With files from Trevor Pritchard