City to investigate why shutting off water took 2 hours after sinkhole occurred - Action News
Home WebMail Saturday, November 23, 2024, 10:14 AM | Calgary | -12.0°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

City to investigate why shutting off water took 2 hours after sinkhole occurred

An investigation into the cause of the Rideau Street sinkhole will look into why it took city crews two hours to stop water from a failed watermain from pouring into the LRT tunnel, Mayor Jim Watson told CBC News.

Mayor says he's been told legitimate reasons for delay, but says it's still worthwhile question

The sinkhole formed at a light rail construction site in downtown Ottawa on June 9, which caused the tunnel to flood. (@notvaleriecrew/Twitter)

An investigation into the cause of the Rideau Street sinkhole will look into why it took city crews two hours to stop water from a failed watermain from pouring into the LRT tunnel, Mayor Jim Watson told CBC News.

The sinkhole occurred shortly after 10:30 a.m. on June 8, but a gas leak forced workers to wait20minutes before they were able to begin shutting the water valves.

That work began at11 a.m. and wasn't finished until 12.35 p.m., according to anemailedstatement sent on behalf ofDixon Weir, the city's general manager of environmental services.

During that time, water from theburstpipesfloodedthe tunnel.

Part of the investigation, says mayor

According to Weir, seven valves had to be shut completely to cut off water to the affected area. Each valve takes between five and15 minutes to close.

"The valves were located at different points on either side of the sinkhole and crews were required to travel from valve to valve in order to close them," said Weir's statement. "The process involves using a specialised tool and can require dozens of rotations, against the force of the pressurized water in the main, to completely close the valve. Care is required as well to ensure that the isolation process does not damage the surrounding water infrastructure further."

It's not clear if the valves were closed one at a time and if so, why.Anotherpublic worksofficial, who is not involved in the sinkhole file and would onlyspeakon background, said valves sometimes need to be shut in sequence. To close more than one valve a time, multiple crews with their own sets of equipment would have to be dispatched.

"I think that's a reasonable question," Watson told CBC News when asked why it took as long as it did to shut off the water. "And obviously we want to have answers to questions like that."

Ottawa Mayor Jim Watson shakes hands with workers at the Rideau Street sinkhole Friday, June 17, 2016. On Saturday, the mayor said Rideau could remain closed to vehicles until after Canada Day. (CBC)

Watson said he wastold by city staffthat there were"legitimate reasons" why shutting off the water takes so long.

Still, he said the issue "will be part of the review that weundertake. What's the cause? And secondly, are there things we could do better on a go-forward basis?"

It's still unknown exactly what caused the June 8watermainbreak or whether the tunnel drilling was a factor.The city's and RTG's investigations into the cause of the sinkholeare expected to take two months.

Damage to tunnel, roadheader, unknown

When engineerswent underground two days after the sinkholeoccurred, they found standing water along300 metres of the tunnel, from about Elgin Street to theRideauCentre. Thewater was as high as three metres at one point,cityofficials estimated.

RTG has been pumping water out of the tunnel ever since.

Pumping out the water is slow going. For one thing, the tunnel opening is more than one kilometre from the sinkhole. Secondly, the water must be treated by RTG's own water-treatment plant built specifically for the LRT project, before being poured into the city's sewers.

The pumping is expected to continue for several days, Watson said.

One of three Rideau Transit Group roadheaders, like this one shown here, is in the tunnel under Rideau Street, at the deepest part of the flooding. It's not known if, or how much, the 135-tonne piece of equipment is damaged. (CBC)

One of RTG's three 135-tonneroadheaders is in the tunnel, where the flooding was the deepest. It isn't known how much, if any, damage has been done to the boring equipment or the tunnel.