Home | WebMail | Register or Login

      Calgary | Regions | Local Traffic Report | Advertise on Action News | Contact

Sign Up

Sign Up

Please fill this form to create an account.

Already have an account? Login here.

OttawaCBC Explains

Why SNC-Lavalin's poor technical score for Stage 2 LRT hardly mattered

The release of new information on the financial scoring for Trillium Line Stage 2 makes one thing crystal clear: when it comes to awarding a big infrastructure project, price reignssupreme.

The scoring system for RFPs weights price too heavily, say experts

The release of new information this week on the financial scoring for Stage 2 LRT makes one thing crystal clear: when it comes to awarding a big infrastructure project, price reigns supreme. (Adrian Wyld/Canadian Press)

This week's unprecedented document dump of previously confidential informationon the controversial Trillium Line Stage 2 procurement has raised umpteen questions about how the contract was awarded.

But the release of new information on the financial scoring makes one thing crystal clear: when it comes to awarding a big infrastructure project, price reignssupreme.

All the concerns the city's technical evaluators had about SNC-Lavalin'sdetailed submission for how they planned to buildStage 2 the absenceof a signalling and train control system, no snow-removal plan orstrategy for using existing trains, wacky designs for stations with no elevators or stairs hardly made any difference in the final analysis.

Because of the way many procurements for public-private partnerships (P3s) are designed, including the one for LRT Stage 2, the scoring isweighted so heavily toward price that technical score almost doesn't matter.

It's not a new observation.

The clich that you get what you pay for takes on a dangerous twist when it comes to the evaluation of price in tenders.- Eddy Jin, procurement consultant

In 2014, Ontario's auditor general said the system of scoring for most P3s "places more weight on a low bid than on technical merits," giving the lowest bidder "a decided edge."

Eddy Jin, aninternational procurement consultant and former director of procurement for University of Toronto, is even more blunt.

"The clich that you get what you pay for takes on a dangerous twist when it comes to the evaluation of price in tenders," wrote Jin in anarticle for a procurement trade journal

It's a scoring scheme, he writes,that "is flawed numerically and is unfair to bidders."

2nd-place bidder had highest technical score

For a year now, CBC has been reporting on the technical scores for the Stage 2 procurement and the factSNC-Lavalin won the contract without meeting the minimum technical gradeof 70 per cent.

But if you looked only at the final scores, you'd never knowthe giant engineering company scored so poorly in the technical round.

SNC-Lavalinscored822 of a possible 1,000 points, whereas as the second-place finisher T-Link a consortium of infrastructure specialistAcciona, investment firm Fengate, and a number of other firms, including local constructors Thomas Cavanagh scored just 641.

But in reality, the bids were much closer than those final scores might indicate.

Consider this: SNC-Lavalin'sbid scored67 per cent in technical, and came with a price tag$1.6 billion;T-Link clocked in with the highest technical score of 86 per cent anda price of $1.7 billion.

SNC-Lavalin's bid was only six per cent cheaper than their primary competitor T-Link, but the difference in the financial scores they were assessed during the bidding process was 62 per cent. (Paul Chiasson/Canadian Press)

How the scoring worked

On the face of it, the scoring seems to give equivalent importance to the technicaland financial submissions, allotting a maximum of 500 points to each category. The two are added together, and whichever bid scores the highestout of a total possible 1,000 points is the preferred choice.

But when you drill down deeper, that description is deceptive.

On the technical side, the scoring is fairly straightforward, with ateam of technical experts reviewing and scoring the bid according toa predetermined score card. (For example, the design part of the submission was worth a total of 225 points.) The evaluators add up all the subtotals, and that sum is essentially the technical score.

SNC-Lavalin scored 336.6 out of 500, or 67 per cent. while T-Link scored 428.9, or 85.7 per cent.

But the financial scoring works much differently.

Financial scoring 'relative'

Of the 500 points available for the financial bid, 50 are set aside to assess the quality of the financing, which generally looks at whether long-term funding is committed. Bidders need to score a minimum of 35 points, or 70 per cent, in this category; SNC-Lavalin scored the minimum 35, while T-Link scored 42.6 points.

The remaining 450 points are allotted to price, and the bidder that comes in the lowest in this caseSNC-Lavalin received the maximum number.So its final score, combining the 450 for price and the 35 for quality of financing, was a whopping 485.

Here's where it gets a bit tricky, however.The other bidders are scored based on how their prices compare to the lowest bid, something Jin describes as a "relative scoring approach" that's used in most P3 procurements.

The difference in the bid prices between SNC-Lavalin and T-Link was six per cent. The difference in their scores was 62 per cent.

In the Stage 2 process, the other bidders had 30 points deducted for every percentage point their pricesexceeded that of SNC-Lavalin. That meantT-Link and its roughly $1.7-billion bid,$100 million more than SNC-Lavalin, scored just 169.82 points.

Combined with its bid quality score,T-Link ended up with just 212.32 points out of 500.

If you looked at the total scores, you might think the prices were much farther apart than they are in reality. In fact, the difference in the bid prices betweenSNC-Lavalin and T-Link wassix per cent, but thedifference in their scores was62 per cent.

(Although T-Link's proposal would have cost $100 million more in the long run, it did call for about $200 million more in spending in the short term, money the city would have had to cover on its own.)

A man with glasses and a close-shaved beard does an interview in a building with people sitting in the background.
Matti Siemiatycki, the interim director of the University of Toronto's School of Cities, says the key is to ensure technical specifications are exceeded while the cost of the project remains reasonable. (Chris Langenzarde/CBC)

Question of value for money

City leaders, including Mayor Jim Watson and city manager Steve Kanellakos, have characterized SNC-Lavalin's bid as good value for taxpayers.

But value and cheapest are not necessarily synonymous.

"We should be looking to deliver projects that provide value for money," saidMatti Siemiatycki, the interim director of the University of Toronto's School of Cities.

"It doesn't necessarily mean the lowest price at all costs, because price can be reduced, but that can also be at the expense of reducing quality the key is to find a technical score [so] that the technical specifications are met and exceeded, and that technical score is being delivered at an affordable price."

Defence is 'high standard' of technical evaluation

In 2015, Siemiatyckico-authored a paper that looked atevaluation scores for 50 projects provided by Infrastructure Ontario.

The paper found that "although technical and financial scores are weighted evenly, their relative impact on the total score is not even."

The report explained that proponents of the scoringdefend the system because, as Infrastructure Ontario told the auditor general back in 2014, "technical scores are subject to a minimum threshold, and proposals not meeting that threshold are removed from consideration."

"By writing good specifications, by ensuring our technical evaluators have a good understanding of those specifications and by ensuring that teams have met a minimum threshold in each of the relevant technical categories, we are ensuring that the teams that pass through are meeting a very high standard of technical," according to the report, quoting an Infrastructure Ontario participant.

Of course, we know that SNC-Lavalin did not meet the minimum threshold although the folks overseeing the procurement have arguedthat because the technical evaluations are somewhat subjective, 67 per cent was close enough.