Still no opening date for Trillium Line as LRT enters final trial phase - Action News
Home WebMail Friday, November 15, 2024, 05:52 AM | Calgary | -5.8°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

Still no opening date for Trillium Line as LRT enters final trial phase

Ottawa'sTrillium Line has now completed the first two phases of trial running, but OC Transpogeneral manager Rene Amilcardeclined on Thursdayto commit toan opening datefor the expanded north-south light rail line.

At least 3 more weeks of work required before north-south expansion can open

A public transit train on a rural section of track on a sunny autumn morning.
An O-Train performs a test run between Limebank and Bowesville stations on Ottawa's Trillium Line on Oct. 7. After weeks of testing, OC Transpo has yet to announce an opening date. (Francis Ferland/CBC)

Ottawa'sTrillium Line has now completed the first two phases of trial running, but OC Transpogeneral manager Rene Amilcardeclined on Thursdayto commit toan opening datefor the expanded north-south light rail line.

Line 2, as it's also known, will soon link Bayview station to Riverside South, with a spur line (Line 4) connectingSouth Keys station to the airport.

Amilcarsaid shewill be in a better position to "be firm" on an opening date at a technical briefing planned for the week of Nov. 18, when she said the launch will be "almost imminent." She alsoconfirmed the system is prepared to deal with bad weather if it coincides with the launch.

Earlier this week, OC Transpoannounced it had successfully completed three weeks of trial running, including a reliability testing phase and an emergency scenario phase,and was about to enter the "final readiness phase," which will take a minimum of three more weeks as OC Transpo obtains regulatory approvals and trains staff.

The Trillium Line, which has been expanded from its originalfive stops, was originally meant to open two years ago but has faced numerous delays.

A red public transit train on a rural track on an autumn morning.
A train is seen during testing on Ottawa's Trillium Line on Oct. 7. (Rebecca Zandbergen/CBC)

Reliability phase aced

The testing phase was obligatory and involved greater monitoring and reporting than previous trials.

Thereliability testing phaseended Oct. 20. Trains left their terminus stations on schedule99.5 per cent of the time, exceedingOC Transpo's goal of98.5 per cent.

In a memo sent Thursday, Amilcarnoted there had been some "vehicle, track, and signal issues" that OC Transpo and TransitNext are still investigating and fixing.

The trial then progressed tothe emergency scenario phase, which involved seven days of testing to gauge how thesystem handleshypothetical emergenciessuch as flooding in the Dow's Lake tunnel or station closures due to fire alarms.

There was no pass-or-fail standard during this phase, OC Transpo said. According to Amilcar's memo, the tests helped with such problems as"optimizing the number of trains in service during disruptions."

Over the three-week final readiness phase,staff will be trained and familiarized with the stations, run more emergency exercisesand complete a "dress rehearsal" to test the system.

OC Transpo must still obtain regulatory approval from Transport Canada, plusa certificate of fitness from the Canadian Transportation Agency.