Winter testing on LRT vehicles was conducted indoors - Action News
Home WebMail Monday, November 11, 2024, 12:54 AM | Calgary | -0.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

Winter testing on LRT vehicles was conducted indoors

Testing conducted to assess whether the city's LRT system could withstand an Ottawa winter was mostly done throughlaboratory simulationsand didn't involve driving the vehicles outside, the city says.

LRT system plagued by problems during 1st winter in service

Winter testing conducted on Ottawa's light rail vehicles was mostly done by simulating extreme temperatures inside a National Research Council lab. (Adrian Wyld/Canadian Press)

Testing conducted to assess whether the city's LRT system could withstand an Ottawa winter was mostly done throughlaboratory simulationsand didn't involve driving the vehicles outside, the city says.

The winter-weather tests, administered in early 2017 inside the National Research Council's "climate chamber," simulated cold, wind, rain, snowand ice conditions and temperatures ranging from 38 C to 38 C, the city said in a summary of the test results posted on Wednesday's citycouncil agenda.

The purpose was to determine whether the Alstom Citadis Spirit light rail vehicles could continue running and keep riders comfortable in a climate with extreme weather and temperature swings.

City officials said the vehicles passed most of the tests.

"The climatic testing of the Citadis Spirit LRV generally demonstrated that the vehicles can withstand Ottawa's most severe weather conditions and provide a safe and comfortable ride for customers," the summary said.

"Seeing that the majority of climatic tests passed without issues and a sound rationale explains each of the deviations, the overall climate comfort and climatic conditions test were considered as passed."

The testing method raises the question of whether the simulation was rigorous enough, as the Confederation Line experienced alitany of problemsduring its first winter in service.

From switch failuresto sensors fooled by blowing snow to power losses, city transportation officials blamed weather formany of the issues which led to delays and replacement buses.

Rideau Transit Group (RTG), the corporate partnership that built the system,would not consent to release of the full results of the 39 tests. Councillors will be able to view the results in the city clerk's office.

The vehicles failed fourtests mainly due to issues related to water leaksbut the city saysAlstom subsequently fixed those problems.

The only testing conducted outside was a series of supplemental tests conducted in OC Transpo's Belfast Yard which involved defrosting the front windshield and some temperature tests.

Add some good to your morning and evening.

More than the headlines. Subscribe to You Otta Know, the CBC Ottawa weekly newsletter.

...

The next issue of You Otta Know will soon be in your inbox.

Discover all CBC newsletters in theSubscription Centre.opens new window

This site is protected by reCAPTCHA and the Google Privacy Policy and Google Terms of Service apply.