Temporary bridge will span Morell River as permanent replacement built - Action News
Home WebMail Saturday, November 23, 2024, 05:03 AM | Calgary | -11.9°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
PEI

Temporary bridge will span Morell River as permanent replacement built

Work is now underway to replace a bridge over the Morell River on Route 2 in Prince Edward Island.

The temporary bridge is expected to be completed by end of September

The temporary bridge that traffic will use for most of the project is expected to be in place by the end of September. (Brian Higgins/CBC)

Construction ofa temporary bridge is underway in Morell, P.E.I., as a major bridge replacement project gets underway.

The bridge over the Morell River on Route 2 is being replaced in a $7 millionproject that is expected to take more than a year to complete.

Work at the site started in mid-June and now crews are in place building a temporary bridge, which all traffic will be detoured onto bythe end of September.

Bridge Engineer Neil Lawless says the new bridge will have no pilings making it easier to inspect and maintain over the projected 75-year lifespan. (Brian Higgins/CBC)

It will be able to handle two lanes of traffic east and west bound with a separatespacefor bikes and pedestrians.

Officials said things will be tight before thetemporary bridge is complete and there may be delays as it is dropped down to one lane of traffic.

"There will be a period five or six weeks or so where we have to go single lane trafficon the east approach,the east side of the bridge," said bridge engineer Neil Lawlesswiththe Department of Transportation and Infrastructure

"That's to give us more room for construction equipmentto construct a temporary bridge at that end of the site."

During that time, a temporarytraffic light will be installed to help direct vehicles.

The temporary bridge is the same one used in Hunter River during the bridge replacement project there over the past few years.

The portable sections are being trucked to Morell and reassembled. Crews are now putting steel pilings into the river on which it will sit.

The Morell Bridge replacement project is expected to be completed by the end of summer 2022. (Brian Higgins/CBC)

The area near the bridge is a busy access point to the river forcommercial oyster fishers as well as recreational anglers and boaters.

The province has built atemporary ramp for their use while construction is underway.

Part of the scope of the project will be to remove even older remains of a former bridge near the site. (Brian Higgins/CBC)

Among the usersare a couple of kayak-rental businesses that depend on river access at this location.

One of the business owners said theyremain busy withlots of people booking online as always but drop-in customers are down.

"Well, it's definitely harder to access the site," saidLaureen Steadman, owner of Bayside Recreation.

"But the province and the village of Morell have done everything they can to accommodate us and give us access to the water."

The area near Morell Bridge is a popular spot for recreational users with two businesses operating rental businesses on the shore. (Brian Higgins/CBC)

The new bridge will be four metres wider than the existing one, with paved shoulders for bikes and walkers.

It will have no piers underneath, making for easier maintenance and fewer obstacles for boat traffic.

Workers will also dismantle the remnants of an even older bridge structure nearby.

The new bridge should be open to traffic next June with the full project expected to be completed by the end of summer in 2022.

More from CBC P.E.I.

With files from Brian Higgins